Microsoft is building a planned 455,000-square-foot, two-story data center called MWH08 in Quincy, Washington. The project is on Microsoft’s existing MWH campus, has cleared local environmental review, and has active construction-stormwater coverage. Public records confirm the permitted project, but they do not confirm a completion date, operating launch, final power demand, cost, or job count.
The project is more specific than the broad description “Microsoft is building a new data center.” MWH08 has its own environmental-review record, site details, utility implications, and construction-related permit history. Understanding those records also requires separating MWH08 from Microsoft’s separate Columbia Data Center and from Grant Public Utility District’s wider transmission-expansion plans.
Key takeaways
- Microsoft’s MWH08 proposal covers a new 455,000-square-foot, two-story industrial data-center building on the company’s existing MWH campus in Quincy.
- The project was submitted on May 29, 2024, under Washington SEPA number 202403581 and City of Quincy file SEPA 2024-008.
- Quincy issued a Determination of Nonsignificance on August 19, 2024; that finding does not mean the building is complete or has no environmental effects.
- Washington Ecology lists construction-stormwater permit WAR313961, with a current permit version effective January 1, 2026, and an expiration date of December 31, 2030.
- The public records reviewed do not establish a confirmed opening date, construction cost, final electrical load, contractor, intended computing workload, or employment total.
What is Microsoft building in Quincy?
Microsoft is proposing MWH08, a new industrial data-center building with approximately 455,000 square feet of floor area and two stories. The project is an expansion of Microsoft’s existing MWH campus rather than evidence of an entirely new Microsoft campus in Quincy.
The proposal includes more than the building shell. The Washington SEPA record for MWH08 lists associated backup-power generator facilities, parking, fuel storage, infrastructure improvements, excavation and fill, irrigation-canal work, and onsite stormwater-retention ponds.
Popular on Amazon
| Project element | Public-record detail |
|---|---|
| Project name | MWH08 Data Center |
| Applicant | Microsoft Corporation |
| Building size | Approximately 455,000 square feet |
| Configuration | Two-story industrial data center |
| Excavation | Approximately 41,000 cubic yards |
| Fill | Approximately 41,000 cubic yards |
| Other facilities | Backup generators, fuel storage, parking, infrastructure, retention ponds, and canal-related work |
Where is MWH08 located?
The SEPA filing places MWH08 at 1515 Port Industrial Way, Quincy, WA 98848, on parcel 042009305, within Microsoft’s existing MWH campus. The proposal record gives approximate coordinates of 47.238972, -119.880329.
Washington Ecology’s facility summary uses 1500 Port Industrial Way for the MWH08 facility. The different street numbers appear in separate agency records and should not automatically be treated as evidence of two projects. The SEPA filing and Ecology facility summary are the relevant records to compare when identifying the site.
Is Microsoft’s Quincy data center under construction?
Microsoft’s Quincy data center project has cleared environmental review and has active construction-stormwater coverage, placing MWH08 in the permitted construction pipeline. The available public records do not establish a precise physical construction stage, groundbreaking date, structural-completion date, commissioning date, or operating launch.
The Tool Desk
Outbyte PC Repair FREERepair Windows errors before they cause bigger problemsFix Now →Outbyte Driver Updater FREEFix the driver behind crashes, sound loss and screen glitchesFind Drivers →Washington Ecology’s facility page lists construction-stormwater permit WAR313961. The page identifies version 2 as effective January 1, 2026, with a permit expiration date of December 31, 2030. The record is useful evidence that construction-related environmental coverage is active; a stormwater permit by itself does not prove that construction is nearly finished or that servers have been installed.
The Ecology facility summary also shows permit data as of July 31, 2026. Because permit status and physical progress are different questions, readers should not interpret the active permit as a confirmed opening schedule. A current site inspection, building-permit record, inspection report, or direct statement from Microsoft or Quincy would be needed to verify the project’s exact stage.
How does MWH08 differ from Microsoft’s Columbia Data Center?
MWH08 and Microsoft’s Columbia Data Center are separate Quincy facilities and should not be combined in an update about the new building.
| Criterion | MWH08 | Columbia Data Center |
|---|---|---|
| Project identity | MWH08 Data Center | Microsoft Columbia Data Center |
| Recorded location | 1515 Port Industrial Way in the SEPA filing; existing MWH campus | 501 Port Industrial Parkway |
| Record type relevant here | SEPA proposal and construction-stormwater coverage | Separate permit and project history |
| Known recent air-permit activity | No project-specific final generator count or complete emissions inventory established in the reviewed records | Ecology approved a notice of construction involving generator operating conditions and bypass-mode operation on March 28, 2025 |
Washington Ecology maintains separate records for Microsoft MWH and Microsoft Columbia. The Ecology data-center permit index is therefore a better starting point than treating every Microsoft permit in Quincy as part of MWH08.
The Columbia air-permit changes reported in late 2024 and early 2025 concern the Columbia facility. Those changes should not be presented as approval for MWH08, and older MWH generator documents should not be treated as the final equipment list for the new building.
Also popular on Amazon
What environmental review has MWH08 received?
Quincy issued a Determination of Nonsignificance, or DNS, for MWH08 on August 19, 2024. The proposal was submitted on May 29, 2024, and the public-comment deadline listed in the SEPA record was September 2, 2024. The city determined that the reviewed proposal would not have a probable significant adverse environmental impact requiring a fuller environmental-impact statement under the circumstances evaluated.
A DNS does not mean MWH08 will have zero environmental effects. The determination means the lead agency concluded that the proposal, based on the information reviewed and applicable requirements, did not require an environmental-impact statement. Construction permits, stormwater controls, utility requirements, mitigation, monitoring, and other regulatory obligations can still apply.
Readers can verify the project name, applicant, site, project scope, determination date, and comment information in the official SEPA record for Microsoft’s MWH08 proposal.
Do these 3 things before closing this tab:
1Scan for outdated or missing drivers - takes under a minute2Clear out junk files and repair common Windows errors3Fix the driver behind crashes, sound loss and screen glitchesHow much water could MWH08 discharge?
The MWH08 project documentation reported estimated clearwater discharge of approximately 3.51 million gallons per year to the Quincy Water Reuse Utility. Clearwater discharge is not the same as total water consumption, so the figure should not be described as MWH08’s total annual water use.
Actual water demand and discharge can vary with cooling-system design, operating load, weather, maintenance, and reuse practices. The available record does not establish the facility’s final potable-water demand, total cooling-water consumption, or final recycled-water use.
The project’s water context is connected to Quincy’s reuse infrastructure. A Quincy Water Reuse Utility agreement involving Microsoft and MWH08 describes the reuse system and Microsoft data-center cooling-water discharges. The agreement and SEPA materials are more precise than a general claim that the facility will “use 3.51 million gallons of water,” because the reported quantity concerns estimated clearwater discharge.
What stormwater and site work are planned?
MWH08 includes approximately 41,000 cubic yards of excavation and approximately 41,000 cubic yards of fill. The proposal also lists onsite stormwater-retention ponds and work involving an irrigation canal. Those features explain why construction-stormwater coverage matters even though the project is located on an established industrial campus.
Construction-stormwater permitting generally addresses runoff and sediment-control requirements during site disturbance. The active record confirms regulatory coverage for the project, but the reviewed sources do not provide a complete current inspection history or establish whether every planned site feature has been completed.
Also popular on Amazon
Ecology’s MWH08 facility summary and permit record provides the permit identifier, effective version, and expiration information that readers can use to track later modifications or compliance records.
What are the power and backup-generator implications?
Quincy attracts data centers in part because Washington Ecology says many of the state’s data centers are located there because of the area’s dependable, lower-cost electricity. MWH08’s proposal includes backup-power generator facilities and fuel storage, while Microsoft’s broader MWH campus has a history of air-permit reviews involving generators and cooling equipment.
Backup generators are generally intended for emergency power and testing rather than ordinary electricity supply. The reviewed records do not establish MWH08’s final generator count, generator size, fuel type, permitted operating hours, emissions limits, or complete air-emissions inventory. Older MWH air-permit documents describe earlier campus phases and should not automatically be assigned to MWH08.
Windows Errors? Fix Them Before They Spread
Repair common Windows errors and clear accumulated junk for a smoother, more stable PC - no reinstall needed.Free scan · no reinstallCrashes, No Sound, or Screen Glitches?
Random freezes, missing sound and display glitches usually trace back to one bad driver. Find and replace yours safely.Free scan · under a minuteGrant PUD is separately planning transmission improvements. The Quincy Transmission Expansion Plan describes efforts to strengthen the grid and add capacity for future energy needs, including a Mountain View Switchyard Expansion and later transmission-line work.
Grant PUD’s regional transmission planning provides important context for data-center growth, but the reviewed utility materials do not establish that MWH08 specifically caused a particular transmission project, nor do they provide a verified MWH08 electrical load or energization date.
What does MWH08 mean for Quincy?
MWH08 is relevant to Quincy because a large data-center expansion can affect several local systems at once: electricity supply and transmission planning, water and wastewater capacity, stormwater management, construction traffic, fuel storage, emergency operations, labor demand, housing pressure, and local revenues.
The public records reviewed verify the project’s physical scope and utility-related infrastructure, but they do not provide reliable figures for total construction jobs, permanent operations jobs, annual tax revenue, construction cost, total power demand, or Microsoft’s investment amount. Those figures should come from Microsoft, the City of Quincy, Grant PUD, or project-specific permit and agreement records rather than industry averages.
Recommended Free Tools
The project’s long-term employment effect also remains unclear. A large construction phase can create temporary work, while permanent staffing depends on the facility’s operating model and computing equipment. No verified employment estimate for MWH08 was found in the reviewed records.
Also popular on Amazon
What remains unknown about Microsoft’s Quincy expansion?
The following important details have not been established by the public records reviewed for this update:
- A confirmed groundbreaking or substantial-completion date.
- A confirmed opening, commissioning, or server-deployment date.
- The project’s construction cost or total Microsoft investment.
- The general contractor and major subcontractors.
- The final electrical capacity or expected ongoing power demand.
- The final generator count, equipment specifications, and MWH08-specific emissions inventory.
- Total water consumption, potable-water demand, and recycled-water use.
- Construction and permanent job totals.
- The intended workload, customer, or whether the building is specifically designed for artificial-intelligence computing.
These are reporting gaps, not evidence that the project has been canceled or completed. Permit status, construction progress, facility commissioning, and commercial operation are separate milestones.
How can readers verify the MWH08 project?
- Check the SEPA record. Search for SEPA number 202403581 or City of Quincy file SEPA 2024-008 in the Washington MWH08 environmental record.
- Check stormwater coverage. Use Ecology’s facility identifier 100002672 and permit number WAR313961 in the MWH08 facility summary.
- Separate the campuses. Confirm whether a document refers to MWH08, Microsoft MWH, or the Columbia Data Center at 501 Port Industrial Parkway.
- Check local building records. A building-permit issuance, inspection history, site-plan amendment, or certificate of occupancy would provide stronger evidence of physical progress than an active stormwater permit alone.
- Check utility records separately. Grant PUD’s transmission plans describe regional capacity work, but a project-specific service agreement or large-load planning document would be needed to connect a particular electrical load to MWH08.
What would provide the next definitive update?
The most useful next documents would be a City of Quincy building-permit and inspection record, a current site-plan amendment, a Microsoft construction update, an Ecology inspection or permit-modification record, and a Grant PUD document identifying MWH08’s expected load or energization schedule.
Microsoft could also clarify the project’s expected completion date, electrical capacity, water-use and reuse estimates, construction and permanent jobs, contractor, and intended workload. Until those details are published or obtained from the relevant agencies, the defensible update is that MWH08 is a documented, environmentally reviewed and stormwater-permitted project—not a facility with a publicly confirmed operating date.
Frequently Asked Questions
Has Microsoft confirmed when the MWH08 data center in Quincy will open?
No. The public records reviewed confirm the MWH08 proposal, environmental review, and active construction-stormwater coverage, but they do not confirm a completion, commissioning, server-deployment, or operating-launch date.
Is MWH08 the same facility as Microsoft’s Columbia Data Center?
No. MWH08 is associated with Microsoft’s existing MWH campus, while the separate Columbia Data Center is recorded at 501 Port Industrial Parkway. Ecology maintains separate project and permit histories for the two facilities.
Does 3.51 million gallons represent MWH08’s total water use?
No. The 3.51-million-gallon figure is an estimated annual clearwater discharge to the Quincy Water Reuse Utility, not a verified total for potable water, cooling-water consumption, or all water used by the facility.
What’s actually slowing this PC down?
Pick the symptom - the matching free tool is one click away.
Did Quincy’s environmental review find that MWH08 would have no environmental effects?
No. Quincy issued a Determination of Nonsignificance on August 19, 2024, meaning the city determined that the reviewed proposal would not have a probable significant adverse environmental impact requiring a full environmental-impact statement. A DNS does not mean the project has zero environmental effects or no continuing permit requirements.
The Bottom Line
Microsoft has a documented plan for MWH08, a 455,000-square-foot, two-story data center on its existing Quincy MWH campus. The project cleared SEPA review in 2024 and has active construction-stormwater coverage as of 2026. The records support describing MWH08 as a permitted project in the construction pipeline, but they do not support claiming that the facility is complete, operational, opening in a particular year, or associated with a known power, cost, or job total.