Repair Windows errors before they cause bigger problemsFix Now →Scan for outdated or missing drivers - takes under a minuteDriver Scan →iTechGuides is reader-supported. When you buy through links on our site, we may earn an affiliate commission. As an Amazon Associate I earn from qualifying purchases. Learn more
Data centers use natural gas in two ways: indirectly, by buying electricity from grids that burn gas, and directly, by operating gas-fired generators or fuel cells on the campus. LNG is the same natural gas cooled to about −260°F so it can be stored and transported as a liquid; the facility vaporizes it before combustion. This arrangement can supply firm power while a grid connection is delayed or can supplement the grid, but it requires fuel infrastructure, air permits, emissions controls and a reliability design sized above the data-center’s instantaneous load.
What “natural-gas powered” means for a data center
A statement that a data center uses natural gas does not necessarily mean the building has gas engines outside its walls. Most facilities receive medium- or high-voltage electricity from a utility. The generating mix behind that electricity varies by region and time. Gas-fired combined-cycle plants are widely used because they are efficient, dispatchable and able to ramp as demand and renewable output change. In the United States, natural gas supplied 43% of total electricity generation in 2023, according to the U.S. Energy Information Administration (EIA, 2024). That is an electricity-system statistic, not a measurement of data centers alone.
The International Energy Agency (IEA) estimated that natural gas supplied more than 40% of the electricity physically consumed by U.S. data centers in 2025, counting both onsite generation and the fuel mix of the grid serving them. Globally, gas supplied 26% of data-center electricity in 2024. These figures describe energy reaching computing facilities, not the percentage of facilities with a gas plant.
Grid electricity from combined-cycle plants
A combined-cycle plant first burns gas in a combustion turbine. Hot exhaust then produces steam for a second, steam turbine cycle. Using the exhaust twice raises efficiency compared with a simple-cycle turbine. EIA describes combined-cycle units as flexible resources that help maintain transmission reliability. A data center connected to such a grid receives the plant’s electricity without handling gas onsite, although the center still carries responsibility for its own backup systems.
#1 Best Overall
- Automatic Home Backup Made Portable: Pair with the Westinghouse WATS200 Automatic Transfer Switch for automatic backup power. This revolutionary, first-of-its-kind technology combines standby convenience with portable versatility. Exclusive to Westinghouse. Switch sold separately.
- Built for Longer Engine Life: The powerful 550cc engine features a pressure lubrication system that delivers oil to critical components, reducing friction and wear. A reusable oil screen captures abrasive particles and contaminants for cleaner oil and long-lasting engine performance.
- Power for sensitive electronics: Less than 5% THD delivers cleaner power for phones, computers and TVs. Copper windings help it run cooler and last longer. Up to 19 hours at 25% load on a 9.5-gallon gas tank, with push-button and remote start.
- Fuel flexibility: Choose gasoline, propane or natural gas. Delivers 11,500 running/14,500 peak watts on gasoline. 50A and 30A outlets pair well with an interlock kit, manual transfer switch or Westinghouse WATS200 ATS system for home backup (sold separately).
- Built-in safety and support: Automatic low-oil shutdown helps protect the engine, while the CO sensor shuts down the generator when elevated carbon monoxide is detected. Backed by a 3-year limited residential warranty and lifetime technical support.
Onsite prime, bridge and standby power
A campus can install gas-fired equipment when transmission capacity is unavailable, an interconnection queue is too slow for the construction schedule, or the operator wants a dispatchable supplement to the grid. Onsite units may serve three different roles:
- Bridge power: temporary generation until a planned transmission connection is energized.
- Prime power: continuous or scheduled production for the computing load.
- Standby or peak support: generation during an outage, a grid constraint or a short demand spike.
The IEA identifies aeroderivative turbines and large reciprocating engines as leading onsite choices because they start quickly, ramp rapidly, can be installed in modules and provide high power density. The U.S. Environmental Protection Agency (EPA) also lists gas-fired engines, microturbines and fuel cells for standby, continuous prime power and combined heat and power (CHP).
Why AI data centers are adding gas generation
AI training and inference clusters create large, concentrated and time-sensitive electrical loads. A developer may be able to complete a building and computing installation before a utility can add substations, high-voltage lines or upstream generation. Installing generation near the load can make electricity available on the construction schedule rather than waiting for the full grid project.
Onsite generation is not sized exactly to the IT nameplate. The IEA’s 2026 analysis says reliable onsite gas-fired electricity for critical and variable data-center demand can require 30% to 70% more generation capacity than the demand itself. The additional equipment covers maintenance outages, sudden peaks, reserve requirements and uncertainty in the computing load. It is an infrastructure-sizing finding, not a claim that every site will operate at those percentages continuously.
Rank #2
- 12500 Peak Watts, 9500 Running Watts (Gasoline); 11200 Peak Watts, 8500 Running Watts (Propane); 9500 Peak Watts, 7500 Running Watts (Natural Gas); Remote Start with Included Key Fob, Electric and Recoil Start; Up to 12 Hours of Run Time on a 6. 6 Gallon Fuel Tank with Fuel Gauge
- Features Two GFCI 120V 5–20R Standard Household Receptacle, One Transfer Switch Ready 120V L14-30R, and One RV Ready 120/240V 14–50R; All Outlets Have Rubber Covers for Added Safety
- Powered by a Heavy Duty 457cc Westinghouse 4-Stroke OHV Engine Featuring a Long-Lasting Cast Iron Sleeve with Automatic Low Oil and Carbon Monoxide (CO) Shutdown, and Digital Hour Meter
- Plug-and-Play: Comes with a Remote Start Key Fob, 12V Battery Charger, Oil, and Oil Funnel, a Tool Kit, and a User’s Manual to Get You Started Right Out of the Box (Minimal Assembly Required)
- All Westinghouse Portable Generators are Functionally Tested in the Factory and May Contain Minimum Residual Oil and/or Fuel Odor; EPA Compliant; Backed By 3-Year Limited Service, Labor, and Parts Coverage and Nationwide Customer Service Network
U.S. developers planned 18.7 gigawatts (GW) of new combined-cycle capacity by 2028, with 4.3 GW already under construction, according to EIA data published in 2025. That pipeline includes projects serving the broader power system; it should not be read as data-center-only capacity. The trend nevertheless shows why gas generation is being considered where large new loads are arriving faster than transmission can be built.
How an onsite natural-gas power system works
Fuel delivery and conditioning
Pipeline gas arrives continuously through a utility or dedicated pipeline at a specified pressure and gas quality. The plant reduces pressure, filters the gas and regulates it for the engines, turbines or fuel processors. A reliable design may use multiple feeds, isolation valves and redundant regulation trains. Exact pressure, flow, pipeline redundancy and storage requirements are site-specific and are not established by a universal data-center standard.
Generation equipment
Reciprocating engines use cylinders and generators to convert combustion into electricity. They are modular and can respond quickly to changing load. Aeroderivative turbines are aircraft-derived gas turbines designed for high power density and fast response. Larger industrial turbines can provide substantial continuous output, while microturbines fit smaller distributed installations. The appropriate technology depends on load profile, required ramp rate, emissions limits, noise limits, cooling design and expected utilization.
Recommended Free Tools
Electrical integration
Generators feed a switchgear lineup that synchronizes with the utility, isolates faults and routes power to critical buses. Uninterruptible power supplies and batteries bridge the milliseconds needed for a generator to start or for a transfer to complete. Operators commonly design multiple independent trains and reserve units so that maintenance on one component does not remove the required capacity. The exact N+1 or N+2 arrangement, black-start sequence and protection settings must be engineered for the particular campus.
Rank #3
- With 13,000 watts of power, the XP13000HXT Tri Fuel generator will keep your whole home running during a storm or power outage, while protecting your family from harmful fumes with CO Alert
- Run your generator on gasoline, propane, or natural gas. With Tri Fuel, we offer the ultimate freedom and flexibility of fuel choice
- Powerful 500cc OHV Engine: At the heart of this generator resides a robust DuroMax engine designed to provide you with the most power.
- The XP13000HXT comes with a push button start, a front facing interface that allows you to change your fuel type in seconds, and a wide variety of outlets including a transfer switch-ready 50 amp outlet
- Push Button Start and Remote Start: Turn on your generator with a simple push of a button, or use the remote to conveniently start your generator from a distance.
Fuel cells
Fuel cells make electricity electrochemically instead of burning gas in an engine. EPA includes them among distributed-generation options for standby, prime power and CHP. In a U.S. Department of Energy demonstration at Microsoft, a 1.5-megawatt fuel-cell generator was paired with cooling equipment, an inverter, transformer and switchgear. A natural-gas fuel cell still needs a reformer or other fuel processor to obtain hydrogen-rich gas. It should not be called zero-emission unless both the fuel and the accounting boundary justify that description.
How LNG reaches a data center
LNG is not a separate fuel molecule. It is natural gas cooled to approximately −260°F (about −162°C), which shrinks its volume to roughly one-six-hundredth of the gaseous volume, according to EIA. That density allows transport by tanker or ISO container and storage where a pipeline is unavailable or cannot deliver enough gas.
- Liquefaction: Natural gas is purified and cooled at a liquefaction facility. The data-center operator may buy LNG from a supplier rather than owning this plant.
- Transport: Tankers, trucks or ISO containers move the cryogenic liquid to the campus or an intermediate terminal.
- Unloading and storage: Transfer lines fill insulated cryogenic tanks. The installation needs unloading equipment, pressure controls and a plan for boil-off gas.
- Vaporization: Vaporizers add heat so LNG becomes a gas. Pressure regulation and gas-quality controls then prepare it for the generator fuel system.
- Generation: Engines, turbines or a fuel processor consume the vaporized gas in the same general manner as pipeline gas.
Some power plants make and store LNG onsite for high-demand periods or when pipeline-delivery capacity is constrained. An LNG-backed data center therefore needs tanks, vaporizers, boil-off-gas handling, hazardous-area controls, truck or marine access and additional permitting. No universal storage duration or cost applies: the answer depends on load, delivery contracts, climate, tank size and local rules.
Pipeline gas versus LNG
| Factor | Pipeline natural gas | LNG |
|---|---|---|
| Physical form | Gas delivered continuously through a pipeline. | Natural gas cooled to about −260°F and stored as a cryogenic liquid. |
| Volume and transport | Requires a connected pipeline and available pressure and capacity. | Occupies about 1/600th the gas volume, enabling tanker, truck or ISO-container delivery. |
| Onsite equipment | Regulation, filtration, metering and gas safety systems. | Insulated tanks, unloading equipment, boil-off management, vaporizers, pressure regulation and gas-quality controls. |
| Main reason to select it | Continuous fuel without scheduled liquid deliveries when pipeline capacity is adequate. | Fuel access where a pipeline is unavailable or constrained, or where stored fuel is needed for high-demand periods. |
| Cost and storage duration | Not stated universally; depends on connection and contract. | Not stated universally; depends on load, tank size, deliveries, climate and permitting. |
LNG is therefore a logistics solution, not automatically a cleaner one. Once vaporized, it is burned in the same classes of equipment as pipeline gas, and its climate impact also includes liquefaction, transport, storage and methane leakage.
Rank #4
- INVERTER BENEFITS, HOME BACKUP POWER: The Westinghouse iGen8200TFc is a tri fuel generator with all the benefits of an inverter, but also with home backup power and a 50A outlet; Gasoline: 6600 running/8200 peak watts, Propane: 5940 running/7380 peak watts, Natural Gas: 5280 running/6560 peak watts
- SAVE FUEL, SAVE MONEY, LESS NOISE: Inverter technology adjusts engine speed to meet power demand, significantly cutting fuel use compared to traditional generators. That's less refills and fuel runs–saving time, money, and hassle. It's also much quieter than open frames, around 60 dBA at 25% load
- TRANSFER SWITCH OR INTERLOCK KIT READY: One 120/240V 14–50R 50A outlet for home backup can run your air conditioner, refrigerator, sump pump, and more–all at once; One RV ready 120V TT-30R 30A outlet; One GFCI 120V 5–20R 20A standard duplex outlet
- LOW THD AND COPPER WINDINGS: With less than 3% THD, it's safe to power electronics like phones, computers and TVs to stay connected during outages, or on jobsites and campsites. Copper windings help the unit make cleaner power, run cooler and last longer
- DURABLE ENGINE WITH SAFETY BUILT-IN: Powered by a heavy duty 298 cc Westinghouse 4-stroke OHV engine with a cast iron sleeve; up to 17 hours of run time on a 3.9 gallon fuel tank at 25% load with automatic low oil shutdown and carbon monoxide (CO) sensor
How gas compares with other data-center power choices
| Option | Strengths relevant to a data center | Issues that must be engineered |
|---|---|---|
| Pipeline gas engines or turbines | Dispatchable output, fast response and continuous fuel delivery where pipeline capacity is reliable. | Combustion emissions, pipeline dependence, noise, heat rejection and air permits. |
| LNG-fueled engines or turbines | Stored fuel and access at sites without sufficient pipeline service. | Cryogenic storage, deliveries, vaporization, boil-off, truck or marine logistics and additional safety controls. |
| Diesel generators | Conventional emergency-generation technology with stored liquid fuel. | Local air pollutants, fuel storage and replenishment; a specific fuel-cell comparison cannot be generalized to every gas system. |
| Batteries and UPS systems | Immediate ride-through and coordination with generator starting and transfer equipment. | Finite energy duration and the need for recharge and a longer-duration source. |
| Fuel cells | Electrochemical generation that EPA lists for standby, prime power and CHP; potentially useful where noise or local-air-pollution limits are strict. | Fuel processing, electrical conversion equipment, hydrogen-rich reformate management and site-specific emissions accounting. |
| Renewables with storage or grid support | Can reduce purchased fossil generation when resource and interconnection conditions permit. | Variable output, land and transmission needs, storage duration and the requirement for firm backup for critical loads. |
The right comparison uses firm capacity, ramp rate, fuel logistics, efficiency at the expected utilization, local air quality, noise, reliability architecture, water use, heat rejection, permitting and full carbon accounting. A technology that looks favorable on one axis may be unsuitable on another.
Emissions, methane and regulation
Combusting natural gas produces carbon dioxide and criteria pollutants such as nitrogen oxides and carbon monoxide. Engines and turbines may require catalytic or selective-reduction equipment, stack monitoring and acoustic treatment. Fuel cells avoid combustion in the cell itself, but a natural-gas system still has upstream emissions and a reformer, and its total result depends on how the fuel is produced.
The value chain can include gas production, gathering, processing, transmission, liquefaction, shipping, storage and regasification. Methane leakage at those stages can materially change the climate comparison. LNG also adds energy use and emissions for liquefaction and transport. Calling LNG “clean” without specifying the comparison boundary and methane assumptions is not technically defensible.
The Tool Desk
Outbyte Driver Updater FREEScan for outdated or missing drivers - takes under a minuteDriver Scan →Outbyte PC Repair FREEClear out junk files and repair common Windows errorsFree Scan →For U.S. projects, EPA’s eGRID database provides generation, emissions, emission rates, heat input and resource-mix data that can support a grid-versus-onsite analysis. EPA’s Greenhouse Gas Reporting Program covers qualifying large sources and fuel suppliers, including LNG storage, LNG import and export, pipelines and stationary combustion. Reporting thresholds and permit conditions depend on the project’s equipment and jurisdiction.
Best Value
- Automatic Home Backup Made Portable: Pair with the Westinghouse WATS200 Automatic Transfer Switch for automatic backup power. This revolutionary, first-of-its-kind technology combines standby convenience with portable versatility. Exclusive to Westinghouse. Switch sold separately.
- Built for Longer Engine Life: The powerful 500cc engine features a pressure lubrication system that delivers oil to critical components, reducing friction and wear. A reusable oil screen captures abrasive particles and contaminants for cleaner oil and long-lasting engine performance.
- Less refueling, easy starting: Runs up to 19 hours at 25% load on a 9.5-gallon gasoline tank. Start with the push of a button or the included remote key fob; backup recoil starting adds flexibility. A built-in fuel gauge makes fuel checks easy.
- Fuel flexibility: Choose gasoline, propane or natural gas. Delivers 10,500 running/13,500 peak watts on gasoline. 50A and 30A outlets pair well with an interlock kit, manual transfer switch or Westinghouse WATS200 ATS system for home backup (sold separately).
- Built-in safety and support: Automatic low-oil shutdown helps protect the engine, while the CO sensor shuts down the generator when elevated carbon monoxide is detected. Backed by a 3-year limited residential warranty and lifetime technical support.
An EPA distributed-generation example found lower carbon dioxide emissions from a particular fuel cell than from a diesel generator under stated technology and operating assumptions. That example does not establish that every natural-gas engine, turbine or fuel cell is cleaner than every diesel installation.
Reliability design for critical computing loads
Gas generation is only one layer of a data-center power architecture. Engineers must coordinate utility service, generators, switchgear, UPS systems, batteries, transfer controls and cooling. Important design questions include:
- Can the plant start without the utility, and can it black-start after a complete outage?
- Are fuel supplies independent enough to survive a pipeline interruption or delayed LNG delivery?
- Does reserve capacity cover the largest unit out of service, planned maintenance and sudden AI-load changes?
- Can generators synchronize and share load without destabilizing sensitive computing equipment?
- Are heat rejection, water availability and CHP opportunities compatible with the site?
- Do air permits allow the proposed annual operating hours, testing schedule and emergency use?
These questions explain why a nameplate megawatt figure alone cannot prove reliability. A plant may have enough theoretical output but still fail its service objective if fuel pressure, switchgear, cooling, controls or maintenance reserves are inadequate.
PC Slower Than It Used to Be?
A free scan shows the junk files, broken settings and background clutter dragging Windows down - then fixes them in one click.Free scan · Windows 10 & 11Crashes, No Sound, or Screen Glitches?
Random freezes, missing sound and display glitches usually trace back to one bad driver. Find and replace yours safely.Free scan · under a minuteHow much gas-fired power will data centers need?
There is no single global number for gas capacity dedicated to data centers. Demand depends on the number and size of campuses, their utilization, the local grid mix, how much onsite generation runs continuously and how much is reserved for outages or peaks. The IEA projects electricity generation serving data centers worldwide to rise from 460 terawatt-hours (TWh) in 2024 to more than 1,000 TWh in 2030 in its base case. That is electricity for data centers from all fuels, not gas alone.
The most defensible planning method is to model the campus load hour by hour, identify the critical and variable portions, apply the required reserve margin, and then test pipeline or LNG delivery under outage and maintenance scenarios. Convert the resulting electrical requirement to fuel flow using the selected equipment’s guaranteed heat rate, then account for part-load operation, startup fuel, testing and CHP heat use. The available data does not provide a universal heat rate, gas-volume conversion or storage-duration assumption, so any precise fuel figure requires project-specific data.
Quick Recap
Practical decision checklist
- Determine whether the gas share is already embedded in the regional grid or whether onsite generation is needed.
- Confirm the utility interconnection date, firm transmission capacity and consequences of delay.
- Define critical, variable and noncritical loads, including the largest step change from AI equipment.
- Compare reciprocating engines, aeroderivative or industrial turbines, microturbines and fuel cells against ramp, efficiency, noise and emissions requirements.
- For pipeline supply, verify pressure, redundancy, curtailment terms and regulator capacity.
- For LNG, size tanks and vaporizers, establish delivery access, manage boil-off and obtain cryogenic-system approvals.
- Design UPS, batteries, switchgear, black-start and reserve capacity as one coordinated system.
- Model direct combustion emissions, upstream methane, LNG logistics and displaced grid emissions using a stated accounting boundary.
- Secure air, construction, hazardous-material, water and greenhouse-gas approvals before committing to the schedule.