Intel’s Ohio One campus is still being built, but its opening has moved years beyond the original 2025 production target. Intel’s latest published schedule places the first fab’s operations in 2030–2031 and the second fab’s operations in 2032. Available statements attribute the slower pace to financial responsibility and alignment with customer demand—not specifically to inclement weather.
When will Intel’s Ohio fab open?
Intel’s February 28, 2025 schedule separates construction completion from the start of operations. Mod 1, the first fab, was expected to finish construction in 2030 and begin operating sometime in 2030–2031. Mod 2 was expected to finish construction in 2031 and begin operating in 2032.
Those are forecast windows, not confirmed grand-opening dates. The original plan, announced in January 2022, targeted production beginning in 2025. Comparing that initial target with the latest published operating window puts the first fab roughly five to six years later.
| Milestone | Original plan | Intel schedule, Feb. 28, 2025 |
|---|---|---|
| Mod 1 construction completion | Not stated in the January 2022 announcement, as summarized by Intel’s project timeline | 2030 |
| Mod 1 operations | Production beginning in 2025 | 2030–2031 |
| Mod 2 construction completion | Not stated in the January 2022 announcement, as summarized by Intel’s project timeline | 2031 |
| Mod 2 operations | Not stated in the January 2022 announcement, as summarized by Intel’s project timeline | 2032 |
The 2026 reporting does not provide a newer, more specific date for when either fab will start production. WOSU/WYSO reported on Aug. 26, 2026, that Intel still described the first fab as on track for completion by 2031, while deadlines remained flexible according to customer demand. That wording does not replace Intel’s distinction between construction completion and operations.
#1 Best Overall
- Get ultra-efficient with Intel Core Ultra desktop processors that improve both performance and efficiency so your PC can run cooler, quieter, and quicker.
- Core and Threads 24 cores (8 P-cores plus 16 E-cores) and 24 threads. Integrated Intel Graphics included
- Performance Hybrid Architecture Integrates two core microarchitectures, prioritizing and distributing workloads to optimize performance
- Performance Unlocked Up to 5.7 GHz unlocked. 40MB Cache
- Compatibility Compatible with Intel 800 series chipset-based motherboards
Did inclement weather cause the latest delay?
No direct attribution to inclement weather appears in the available statements about the schedule changes. Intel’s February 2025 update instead said it would continue construction at a slower pace while retaining flexibility to accelerate work and operations if customer demand warranted. Naga Chandrasekaran, Intel’s executive vice president, chief global operations officer and general manager of Intel Foundry Manufacturing, described the approach as financially responsible.
That does not prove weather had no effect on any particular construction activity. It means weather is not established as the cause of the reported schedule slip. Without a direct statement or documented weather-related interruption, it would be inaccurate to describe the latest delay as weather-driven.
Rank #2
- Game without compromise. Play harder and work smarter with Intel Core 14th Gen processors
- 24 cores (8 P-cores plus 16 E-cores) and 32 threads. Integrated Intel UHD Graphics 770 included
- Leading max clock speed of up to 6.0 GHz gives you smoother game play, higher frame rates, and rapid responsiveness
- Compatible with Intel 600-series (with potential BIOS update) or 700-series chipset-based motherboards
- DDR4 and DDR5 platform support cuts your load times and gives you the space to run the most demanding games
Why is construction moving more slowly?
Intel’s stated rationale is to pace the project responsibly and align its completion and production plans with demand and business conditions. In its February 28, 2025 update, Chandrasekaran wrote: “We are taking a prudent approach to ensure we complete the project in a financially responsible manner that sets up Ohio One for success well into the future.” He also said construction would continue at a slower pace, with flexibility to accelerate if customer demand warranted.
In August 2026, WOSU/WYSO likewise reported that work remained underway at a slower pace and that project deadlines were flexible based on customer demand. The sources do not identify a single new event as the cause of each schedule change; the supported explanation is deliberate pacing rather than a confirmed weather disruption.
Recommended Free Tools
Rank #3
- Intel Core i7 3.60 GHz processor offers more cache space and the hyper-threading architecture delivers high performance for demanding applications with better onboard graphics and faster turbo boost
- The Socket LGA-1700 socket allows processor to be placed on the PCB without soldering
- 11 MB L2 and 25 MB L3 cache offers supreme performance for computation intensive apps
- Intel 7 Architecture enables improved performance per watt and micro architecture makes it power-efficient
Is Intel’s Ohio fab still being built?
Yes. The project is delayed, but the available reporting and municipal updates do not describe it as canceled. WOSU/WYSO reported in August 2026 that work was continuing. New Albany’s municipal construction page says Intel has reiterated its full commitment and lists related infrastructure work in 2026.
Ohio One is a planned two-fab semiconductor campus in New Albany, Licking County. Intel’s project page describes an investment of more than $28 billion. In February 2025, Intel also reported that work on the project had involved more than 6.4 million work hours and more than 200,000 cubic yards of concrete. Those figures describe progress at that time; they do not establish a completion percentage or a current construction pace.
Rank #4
- Next‑Gen Platform Support: Compatible with Intel 800 Series Chipset‑based motherboards with LGA1851 Socket enabling PCIe 5.0/4.0 and high‑speed DDR5 memory (up to 7200 MT/s).
- High‑Performance Core Configuration: Features up to 24 cores (8 P‑cores + 16 E‑cores) for demanding gaming and creator
- Ultra‑Fast Boost Clocks: Reaches up to 5.5 GHz max turbo frequency for top‑tier responsiveness and performance
- Built for Enthusiasts: Unlocked for performance tuning when paired with Intel Z‑series chipsets, making it ideal for overclockers and power users.
- Robust Power & Thermal Design: Engineered with 125W base power and 250W max turbo power to sustain high‑intensity
What the schedule means for the grand opening
There is not yet a supported date for a ribbon-cutting ceremony. Construction completion, the start of fab operations and a public grand opening are different milestones, and the published schedule supplies windows for the first two—not a ceremony date. New Albany Mayor Sloan Spalding told WOSU/WYSO that the region was anticipating a day to gather for a ribbon cutting, but did not give a date.
Quick Recap
Product prices and availability are accurate as of the date/time indicated and are subject to change. Any price and availability information displayed on Amazon at the time of purchase will apply.
Do these 3 things before closing this tab:
1Repair Windows errors before they cause bigger problems2Scan for outdated or missing drivers - takes under a minute3Clear out junk files and repair common Windows errors