The Tool Desk
Outbyte PC Repair FREEClear out junk files and repair common Windows errorsFree Scan →Outbyte Driver Updater FREEScan for outdated or missing drivers - takes under a minuteDriver Scan →Load banks let commissioning teams test a data center’s electrical and cooling systems before production servers are installed. The most useful plans coordinate electrical loading with realistic heat and airflow simulation, then set project-specific scenarios and acceptance criteria with the engineer of record and installing trades.
What load banks do in data center commissioning
A load bank applies a controlled electrical load so teams can exercise power infrastructure without relying on production IT equipment. In a data center, the test can also assess heat rejection: most power delivered to IT equipment becomes heat, so reproducing the thermal load helps reveal how cooling responds. ASHRAE describes resistive load banks as a way to test electrical and heat-rejection systems together in its Chapter 20, Data Centers and Telecommunication Facilities.
| # | Preview | Product | Price | |
|---|---|---|---|---|
| 1 |
|
UPS & Industrial Battery Bank Conductance Test Log Book: Uninterruptible Power Supply Maintenance... | $22.99 | Buy on Amazon |
Load-bank testing is not a substitute for testing the operational IT environment. It is a controlled means of exercising facility systems before that environment is available, or as part of a project-defined test sequence.
Choose a load solution that matches the test
Equipment choice should follow the electrical and thermal behavior the test needs to represent, rather than a single universal configuration.
#1 Best Overall
Resistive load banks
Resistive units provide controllable electrical load and generate heat. Their use can connect electrical testing with observation of heat-rejection performance, but the arrangement still needs to reflect the project’s design and test objectives. ASHRAE discusses this combined use in its data-center guidance.
Purpose-built heaters
The U.S. Green Building Council recommends purpose-built heaters for partial- and full-load testing to simulate IT heat. This option is relevant when the goal includes evaluating cooling under simulated thermal load; specify the electrical and placement requirements for the actual project. See the USGBC Fundamental Commissioning and Verification Reference Guide: Data Centers.
Server simulators
Server simulators can be sized and arranged to reflect IT rack conditions, including airflow. ASHRAE describes them as a best-practice approach. They can make rack-level thermal conditions more representative than a test that considers only total facility load, but the simulator size, arrangement, and airflow assumptions need to match the commissioning plan.
Plan the test around facility requirements
ASHRAE’s guidance is explicit about coordination: “The CxP should develop a load bank plan in collaboration with the engineer of record and the installing trades to plan and execute load testing.” The plan should tie equipment and test conditions to owner requirements, design documents, commissioning scope, manufacturer instructions, and applicable local requirements.
Quick wins for a faster PC:
Repair Windows errors before they cause bigger problemsFix Now →Scan for outdated or missing drivers - takes under a minuteDriver Scan →Compare candidate equipment and arrangements against the project’s actual needs:
- Electrical representation: required load, capacity, power factor, and other load characteristics.
- Distribution and connection: connection points, temporary distribution, space, access, staging, and safe working arrangements.
- Thermal representation: heat output, rack-level airflow pattern, heat handling, and the ability to observe the intended cooling response.
- Control and evidence: controllability, instrumentation, logging, and how results will be compared with acceptance criteria.
- Execution: equipment availability, deployment schedule, test windows, responsibilities, and whether the scope is component testing or integrated commissioning.
These are planning criteria, not a ranking of products. Neither ASHRAE nor USGBC establishes one load-bank capacity, layout, or pass threshold that applies to every facility. Set those values from the project’s requirements and documents.
Coordinate electrical and thermal objectives
Start coordination early enough to settle load capacity, equipment placement, temporary connections and distribution, controls, heat handling, access, test windows, and team roles. Agree on test scenarios and acceptance criteria before the load equipment arrives. Keep the two objectives distinct in the plan: an electrical test evaluates power-system response under load, while a thermal simulation is needed to observe cooling behavior under simulated IT heat.
Check that the chosen placement and airflow arrangement represent the conditions the team intends to evaluate. For example, a facility-level load target alone does not establish that rack-level airflow is represented; server simulators may be appropriate where the project calls for that detail.
What’s actually slowing this PC down?
Pick the symptom - the matching free tool is one click away.
Distinguish component tests from integrated systems testing
A component capacity check exercises a particular item or subsystem under load. Integrated systems testing addresses how facility subsystems respond together, including under planned anomalies. These tests answer different questions, so the commissioning plan should state which are in scope and define their scenarios and acceptance criteria.
Aggreko describes a five-level commissioning framework in which equipment checks progress toward assessing equipment working together under load. Level names and definitions depend on the framework being used; the project’s adopted commissioning plan, not a vendor framework label by itself, governs the test scope. Its data center commissioning overview provides the vendor’s description.
Use standards and guidance within their stated scope
ASHRAE and USGBC provide relevant commissioning guidance, but project specifications and equipment manufacturer documentation determine the actual procedure and acceptance criteria. Verify current editions, local adoption, and applicability for the facility before using standards or guidance as project requirements.
IEEE’s P4200 data-center interconnection project page concerns interconnection requirements and data-center capabilities; it should not be treated as a load-bank test procedure.
Quick Recap
Product prices and availability are accurate as of the date/time indicated and are subject to change. Any price and availability information displayed on Amazon at the time of purchase will apply.

