To make one Asana task wait for another, open the task that must wait, select Add dependencies in its details pane, and choose the task that must happen first. The waiting task will be marked Blocked by the prerequisite task. You can also create and inspect dependencies in a project list, Timeline, or Gantt view.

Set a dependency from task details

  1. Open the task that cannot start or finish until another task is done.

  2. In the task details pane, select Add dependencies or find the Dependencies field.

  3. Type the name of the task that must happen first. Where supported, you can paste that task’s URL instead.

    Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.
  4. Select the matching task from the suggestions. The task you opened is now Blocked by the selected task.

  5. Check the direction before saving or moving on: Blocked by means this task is waiting; Blocking means this task is holding up another one.

You can add more than one prerequisite to a task, and a prerequisite can block more than one task. To remove a link, hover over its dependency indicator and select the X. For Asana’s instructions, see Task dependencies.

Choose the best place to create or view the link

Where you work How to use it Best suited for
Task details Open the waiting task and use Add dependencies or its Dependencies field. Creating a link when you know which task is waiting and which task is the prerequisite.
Project list Use the project’s field or column controls to add Blocked by and Blocking columns. Reviewing dependency direction across tasks in a list.
Timeline Hover over a task to reveal its connector, then drag the connector to the task that depends on it. Creating or checking links alongside a visual schedule.
Gantt Hover over a task block and drag its dependency handle to another task; use the dependency-type selector after linking. Working with a Gantt schedule or choosing a specific dependency type.

In Timeline, a grey connector indicates no date conflict; a red connector indicates a potential conflict, such as a dependent task starting before its prerequisite is complete. See Asana’s guides to managing tasks and dependencies with Timeline and Gantt view.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Understand dependency direction and types

Blocked by and Blocking describe the same link from opposite sides. If task B cannot proceed until task A is done, B is Blocked by A, while A is Blocking B. Thinking through the relationship this way helps prevent linking the right tasks in the wrong direction.

Asana documents four dependency types. Choose the one that matches how the work overlaps; the type selector is available in Gantt after you create the link.

Rank #3
Sale
Beautiful To Do List Notebook - Aesthetic Undated ADHD Daily Planner Gift
  • Daily Focus To Stay On Track: Ready to enjoy more free time? Staying organized has never been easier - the daily to do notebook features space for daily to do’s, notes, health & fitness tracking, a meal planner and appointments
  • Boost Your Productivity: Use the daily to do list notepad (8.5x6.4”) to plan & work smarter not harder for efficient daily task management; with the undated to do planner you can plan out 120 days and completely cultivate new planning habits for a major shift in your life
  • Great To Start Any Time: The daily to do planner is undated, so you can make each day count & start getting rid of that nasty procrastination today, no more wasting time! Everything settled? Tear-off the page & celebrate another successful day - what a feeling
  • Beautiful Modern Minimalistic Design: Planning is so much more fun when using this eye-catching planner with to do list with its modern look, black spiral, elastic band and a back pocket for extra space
  • Stay Motivated & Achieve Great Things: While tracking progress is the greatest motivator in itself, the daily list planner even makes the journey more beautiful with motivational quotes & a dedicated space for your gratitude practice
Type Meaning Example
Finish-to-Start (FS) The first task must finish before the second starts. Testing begins after implementation is complete.
Finish-to-Finish (FF) The first task must finish before the second can finish. Documentation may begin earlier, but cannot be finished until the feature is complete.
Start-to-Start (SS) The first task must start before the second can start. Monitoring begins once a rollout starts.
Start-to-Finish (SF) The first task must start before the second can finish. A handover task starts before the outgoing coverage task ends.

For Asana’s definitions, see Dependency types.

Know when dependent dates will shift

Creating a dependency does not by itself guarantee that Asana will move dates. Auto-shifting is a separate project setting, and it depends on linked tasks having relevant due dates, the chosen shifting behavior, and the tasks not being completed. When you change dates outside Timeline or Gantt, Asana describes a preview modal showing the resulting dates for dependent tasks.

Asana documents three ways to handle schedule buffer:

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.
  • Maintain buffer: preserve the gap between dependent tasks when dates shift.

    Rank #4
    Sale
    Beautiful Daily Planner And Notebook With Hourly Schedule - Spiral Notebook
    • Easily Stay On Track & Make The Most of Your Time: ZICOTOs’ daily planner makes it easier than ever for you to stay organized, reduce stress & enjoy more free time! Arrange your schedule, priorities, to do’s and jot down plans & ideas on the daily notes section
    • Smartly Plan Ahead & Boost Your Productivity: Absolutely clever & efficient! With the planner notebook you can break down your daily tasks into half-hourly focus blocks and map out priorities & follow-up duties to keep your day on track and enhance productivity
    • Plenty Of Space For Efficient Planning: Stay focused & manage your time wisely! The 9.3x6.3” (inner pages) work planner & organizer notebook offers ample space for 80 days of life-changing planning with each day being spread across 2 pages - set yourself up for purposeful days
    • Now Is The Best Time To Start: The daily planner is undated so you can start to add structure to your schedule and cultivate new planning habits right away! Beat procrastination, boost happiness & make each day count with the hourly planner
    • Adds Beauty To Daily Planning: A gorgeous champagne pink cover, chic gold foil letters, a golden ring wire and a clean, easy-to-use layout - enjoy the gorgeous and modern minimalist design of the undated daily planner!
  • Consume buffer: use the gap as schedule changes occur.

  • Ignore buffer: do not preserve or consume that gap when shifting dates. Asana’s auto-shifting documentation describes None as the default; it says only new projects with a Gantt tab are set to Consume buffer.

Timeline has a route to project dependency settings through the project’s options. Check the setting in your project before relying on automatic date changes. See Asana’s auto-shift dates documentation and Timeline guide.

Free tools Windows power users keep installed

One-click scans. No signup required.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.
Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.Support on Ko-Fi

Notifications and optional automation

Asana says the assignee of a dependent task is notified when its prerequisite is marked complete, or when the prerequisite’s due date is changed or removed. If the waiting task has multiple prerequisites, its assignee receives one notification after all of them are complete.

You can also create a project rule triggered when a task is no longer blocked. The rule can then take actions such as setting a due date, moving the task to a section, or adding collaborators. This is optional; it is not needed to create the dependency. See Asana’s guide to using dependencies to kick work off at the right time.

Availability

Asana’s cited help pages list dependencies and Timeline for Starter, Advanced, Enterprise, Enterprise+, and certain legacy tiers, including Premium, Business, and Legacy Enterprise. Plan names and entitlements can change, so check the current availability in your Asana account rather than treating those help-page lists as a current pricing comparison.