For a pressurized-water reactor, replacing steam generators usually keeps the unit offline for about 75 to 80 days when the work is combined with a normal refueling outage. Documented projects range from 63 days 13 hours to about 121 days, so a two-and-a-half-month planning assumption is reasonable, while a complex project can approach four months.

Those figures describe the entire outage—from shutdown and defueling through testing, fuel loading and authorization to restart—not merely the time spent lifting out and installing the generators.

The practical outage range

The most useful broad benchmark is approximately 75 days. A Powers Engineering filing in an Environmental Protection Agency docket cites a 75-day average for a steam-generator replacement outage. Diablo Canyon environmental documentation gives a 75–80-day duration for an outage that included steam-generator replacement.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Real projects show why that number should be treated as a planning range rather than a promise. Callaway’s 2005 outage, which replaced four steam generators, lasted 63 days and 13 hours. A project-management case study estimated approximately 95 days for Catawba. The U.S. Energy Information Administration recorded 121 days for the 2022 Watts Bar Unit 2 refueling outage that included steam-generator replacement.

#1 Best Overall
Sale
Compressed Air Duster,130000RPM Super Power Cordless Air Duster,Rechargeable Brushless Blower,3 Gear Adjustable Blower with LED Light,Dust Remover for Computer/House/Outdoor/Car
  • Powerful Turbo Fan:CAGIWIRU Electric Air Duster have reached speed up to 130000RPM,Can efficient remove dust and debris.With LED light and Three Adjustable Speed to meet with different cleaning tasks.
  • With Attached USB C Fasting Charging cable.Charing 3 hours,Enjoy up to 240 minutes of use on the lowest setting, For third speed can use for 25mins.with four charging options to meet with your needs.
  • Wide Application: attached 5 different nozzles,making it suitable for a variety of scenes, such as car,pet, pc, keyboards, and other electronic devices. It also serves for office and home clean duster.
  • Handy Design & Portable:Cordless air duster electric nozzle is Light weight and small size, design and comfortable to hold and space saving, convenient to carry around. You can put it in your room or inside the car without taking up space.
  • Economical &Reusable: Built durable materials with a long-lasting battery,our CAGIWIRU air duster it's a sustainable alternative to disposable air cans.

On that evidence, a reasonable public answer is roughly 60 to 120 days, with 75–80 days as the central benchmark. The shorter figure reflects an exceptionally well-executed project; the longer figures include more conservative planning or a larger amount of work in the same outage.

Project Total offline time Generators Plan or actual Concurrent work and qualification
Callaway, 2005 63 days 13 hours Four Actual Outage including replacement; Ameren Missouri described it as a world record at the time for replacing four generators in an outage.
Diablo Canyon 75–80 days Not stated Documented outage duration Steam-generator replacement combined with the refueling outage.
Catawba Approximately 95 days Not stated Project estimate Planning figure; the source does not establish an actual final duration.
Watts Bar Unit 2, 2022 121 days Not stated Planned refueling-outage duration Replacement was part of the refueling outage; it is not presented as a universal actual duration for every project.

The comparison is not an apples-to-apples performance ranking. Unit design, access arrangements, the amount of refueling and maintenance performed at the same time, and whether the number is a plan or a final result all change the total.

Why the replacement takes weeks instead of days

A steam generator is a large heat-exchanger vessel between two systems. Reactor coolant transfers heat through thousands of tubes to water on the secondary side, where steam is produced for the turbine. The vessel is connected to large-diameter primary and secondary piping, structural supports, insulation, instruments and safety-related systems. Replacing it is therefore a major plant modification, not a simple component swap.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

The reactor must normally be shut down and defueled first, which is why utilities schedule the work during a refueling outage. The replacement sequence then combines heavy construction, nuclear-quality welding, inspection, testing and regulatory controls.

1. Shut down and defuel the reactor

The unit is taken offline and the reactor is placed in the refueling configuration. Fuel is removed so workers can perform work inside containment and on the reactor coolant system under the procedures required for the outage. This front-end work is part of the outage clock even though it is not a steam-generator lifting operation.

2. Create the access opening and heavy-load path

Steam generators are too large to remove through ordinary equipment doors. The outage team must establish a route for the old vessels and the replacements, which can require opening or modifying the containment structure. Cranes, transport fixtures, temporary supports and load-control procedures are set up before a vessel is moved. The geometry of the containment and the available heavy-lift arrangement can be a defining schedule constraint.

Rank #2
EVEO® Screen Cleaner Spray Kit (Streak-Free) TV Screen Cleaner for Smart TV, Lcd, LEd, Oled | Computer Screen Cleaner Spray and Wipe Microfiber Cloth - TV, Monitor, Laptop, iPad, Car - 6.7oz 1 Pack
  • Screen Cleaner is Your Screen’s New Bestfriend! - EVEO is proud to present a screen cleaner that’s perfectly suited for your TV. Meet your new screen cleaner, computer screen cleaner, laptop cleaner, iPad cleaner, Macbook,tv cleaner or any other electronic device. Our screen cleaner spray and wipe along with the included plush microfiber cloth, easily removes dust, fingerprints & other smudges on the screen’s surface. Clean effectively for a streak-free screen
  • Gentle on your Screens - Our screen cleaner spray and wipes is compatible to be used even for the most sensitive LCD, LED, CRT, and OLED screens in proper use. Be at ease knowing that this product is compatible with all the major brands: LG, SONY, Samsung, Sharp, iPad, iPhone, Android screens, Kindle, PC monitors - we’ve got you covered! Can be used as LCD screen cleaner, tv cleaner, smart tv screen cleaner, and more
  • Premium Super Soft Plush Microfiber Cloth - Included in this efficient screen cleaning kit. This screen cleaner spray and wipe has our signature plush microfiber cloth specially designed to comply with screens and monitors and leave them streak-free. Has been shown to effectively absorbs stubborn stains, zero streaks, and no fiber shedding. Always use this together with our screen cleaner for the best results
  • Easy-to-Use Screen Cleaner Kit + microfiber cleaning cloth - The EVEO Screen Cleaning Kit will easily be your new favorite tool when it comes to taking care of the things you love most, quick and easy solution for a streak-free screen. Simply screw on the sprayer gun on the screen cleaner bottle. Spray the cleaning liquid onto the microfiber cloth, then wipe the screen until desired cleanliness & shine is achieved.
  • Quality Screen Care Kit Worth Purchasing - Enjoy a convenient Screen Cleaner anytime, anywhere you need it. Your satisfaction is our top priority. We stand behind the quality of our products and that’s why, you shouldn’t be worrying at all. We manufacture the Best Screen Cleaner. and can be used for laptop cleaning kit, laptop screen cleaner, tv screen cleaner for smart tv. MacBook screen cleaner, monitor cleaner or screen cleaner spray for electronic devices with microfiber cleaning cloth

3. Disconnect piping, supports and services

Workers separate the generator from reactor-coolant piping and from the secondary steam and feedwater systems. They also disconnect supports, insulation, drains, vents, instrumentation and other attached services. These interfaces must be documented and controlled because each one has to be restored in the correct configuration.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

4. Remove the old generators

After the connections are cut and the load path is ready, the old vessels are moved out of containment. The lift itself may be relatively short compared with the preparation and restoration work around it. Rigging, clearances, temporary structures and radiological and industrial controls determine how quickly the move can proceed.

5. Set and weld the replacements

The new generators are positioned, aligned and connected. Large welds on the primary and secondary boundaries require qualified procedures, controlled work conditions and time for inspection. Any repair or rework discovered during welding can affect the critical path.

6. Perform nondestructive examination and inspections

Welds and other safety-significant work are examined using the required nondestructive methods. Inspectors verify that the completed joints, supports, tubing-related components and installed services meet the applicable design and quality requirements. Hold points can prevent the outage from moving to the next phase until results are accepted.

7. Restore insulation, instruments and supports

Once the pressure-boundary work is accepted, crews reinstall insulation and reconnect instruments, cables, drains, vents, supports and operating equipment. The replacement is not complete until the surrounding systems are returned to their design configuration.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

8. Test, reload fuel and restart

The plant performs pressure tests, leak checks, functional tests and system walkdowns. Operators then reload fuel and work through the controlled startup sequence. Licensing and regulatory authorization, as well as completion of required documentation, are part of the return-to-service process. These final activities explain why the reactor can remain offline after the physical installation appears finished.

Rank #3
Sale
BladeHawks RGB Gaming Mouse Pad Extra Large Extended 31.5x12 Inch-Black | LED mouse pad with 14 lighting modes, covers keyboard & mouse, anti-slip rubber base, waterproof surface, USB powered
  • 【Large size】:Measuring 800 x 300 mm/ 31. 5×12 inches, which is wider and taller than others. Large mouse pad can perfectly fit your keyboard and mouse of any size, and there is also ample space for peripherals such as phones, tablets, etc.
  • 【LED backlight mouse pad】:Blade Hawks RGB mouse pad provides 7 static modes and 7 dynamic modes will give you the options you are looking for. Power-off memory function remembers the last lighting mode you selected. The super glow fiber Chroma will give you a colorful gaming setup that you want.
  • 【Anti-slip rubber base】:Made from Natural rubber, this gaming mousepad will firmly grip your desktop, allowing you to enjoy the ultimate precision in the games you are most passionate about. It also comes with a texture that enhances this ability even further.
  • 【Smooth and waterproof surface】: Micro-textured cloth surface, for extremely precise mouse control and a smooth movement. When liquid splashes on the gaming mouse pad, it forms water droplets and slides down. Will not delay your work or gameplay.
  • 【Plug and play】: This mouse and keyboard pad is powered by USB, plug and play, no driver required. One button control light modes. Press one time to change the lighting mode, press twice to change the brightness, press and hold about 3 seconds turn ON/OFF.

Why replacement outages are longer than ordinary refueling outages

Steam-generator replacement is commonly about twice as long as an ordinary refueling outage because it adds a large construction project to the normal fuel-cycle work. A standard refueling outage already includes defueling, inspections, maintenance, repairs, fuel loading and startup testing. Replacement adds containment access, heavy lifts, major piping cuts, high-integrity welds, examinations and system restoration.

Utilities often combine other planned maintenance with the same shutdown to avoid taking the reactor offline again. That strategy can improve long-term availability, but it also means the longest or most uncertain task can determine the return date for the entire unit.

What determines whether the outage is 65 days or 120 days?

Reactor and containment design

Different plants provide different routes for removing a generator. The size and geometry of containment, the location of equipment, and whether a large opening can be made and restored efficiently affect both preparation and restoration time.

Free tools Windows power users keep installed

One-click scans. No signup required.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Number and arrangement of generators

Replacing four vessels requires more lifts, more piping interfaces and more welds than replacing a smaller set. The physical arrangement also matters: access and interference between components can make one plant faster or slower than another even when the generator count is similar.

Concurrent refueling and maintenance scope

The published duration may include only the replacement and routine refueling work, or it may include a substantial package of inspections and maintenance. The outage ends only when all critical work is complete, so unrelated emergent work can become schedule-driving.

Weld and examination results

Welding and nondestructive examination are sequential activities. A weld repair, a failed examination or additional inspection can require work to be repeated before testing begins. This is why a schedule with little contingency can move quickly from an on-time forecast to a late return.

Rank #4
Sale
Vaydeer Wrist Rest for Keyboard and Mouse, Computer Ergonomic Wrist Support Pad, Soft Memory Foam Arm Cushion for Desk, Palm Hand Office Laptop Typing
  • 【Softer and More Comfortable】Vaydeer wrist rest has unique diamond pattern, which is the combination of softness and aesthetics. The materials of wrist rest are improved into higher quality memory foam and covered with silky smooth lycra. The computer wrist rest makes you as comfortable and cushiony as like rest your wrists on clouds.
  • 【Ergonomic Wrist Saver】The wrist rests for keyboard and mouse comes with a 17.32×3.15×0.83 inch keyboard wrist pad and a 5.94×3.15×0.83 inch mouse wrist support. Based on ergonomic design, the unique concave shape is the perfect fit for your wrist joints. The wrist rest pad fits most computer keyboards and laptops, improve hand and wrist posture, release your wrist and arm stress.
  • 【Non-Slip Rubber Bottom】Featuring an anti-skid silicone base on the bottom, this wrist keyboard support stays firmly in place on your desk, preventing the padding from sliding around, ensuring stable and consistent wrist support during extended computer sessions.
  • 【Better Experience & Pain Relief】Our keyboard arm rest is beneficial to alleviate the soreness caused by direct contact and friction between your arm and a hard desk surface, reducing the risk of wrist fatigue or carpal tunnel. The soft texture of memory foam can evenly distribute the pressure around your wrists and provide good support with just enough give.
  • 【Helpful in Multiple Scenarios】Whether you're working, studying, writing, typing, gaming, this keyboard and mouse rest combo is an essential accessory to add comfort and support to your hands and wrists. It’s also a great gift for men, women, family, friend, coworker, gamer, teacher, etc.

Licensing and regulatory hold points

Safety-related modifications require documented reviews and approvals. A plant may be physically ready but unable to restart until required tests, records and regulatory hold points are complete.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Emergent findings and equipment problems

Inspection can reveal conditions that were not visible during planning. Equipment failures, damaged supports, unexpected contamination or access problems can add work. The final forecast should therefore be updated as inspections and tests produce results, rather than treated as fixed when the outage begins.

Planned duration versus actual return date

A planned outage duration is an estimate, not a guarantee. The Catawba figure of approximately 95 days is explicitly a project estimate, while the Watts Bar Unit 2 figure of 121 days is reported as a planned 2022 refueling-outage duration. Callaway’s 63-day-13-hour result is an actual historical accomplishment, not a promise that another plant can match it.

Koeberg Unit 2 illustrates the operational decision behind schedule changes. After a final review indicated a high likelihood of returning later than planned, the utility deferred the steam-generator replacement to a later outage to protect electricity supply during the winter-demand period. Deferral can be preferable to starting a high-risk project when the forecast no longer supports a safe, reliable return date.

Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.Support on Ko-Fi

What a 75-day schedule usually includes

The phrase “75-day replacement outage” should be read as a total plant outage. A simplified schedule has overlapping work fronts rather than one task followed by another:

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.
  • Early outage: shutdown, defueling, containment preparation and installation of temporary lifting and support equipment.
  • Removal phase: cutting and disconnecting piping and services, moving the old generators and preparing the interfaces.
  • Installation phase: setting the new vessels, alignment, welding and reconnection.
  • Verification phase: nondestructive examination, pressure and leak testing, instrumentation checks and system walkdowns.
  • Startup phase: fuel loading, controlled reactor startup, functional testing and authorization to return to power.

Work can proceed in parallel, but tasks on the critical path cannot be skipped. A delay in a primary-boundary weld, for example, can hold up testing and startup even if refueling work is already complete.

Best Value
Sale
Under Desk Cable Management Tray No Drill, Metal Mesh Cable Management Under Desk with Clamp Mount, 2 Hole Cable Tray with Wire Management and Cord Organizer for Home Office Standing Desk
  • 【No Drill Mounted】Cable management tray can be assembled in as little as 3 minutes or less-simply. Side clips easily clampe the edge of desk, pass through the holes on the sides, and secure excess cables with baskets. Desk cable management supports inward or outward installation to meet your needs in different scenarios, and provides you with great convenience when collecting and organizing wires.
  • 【Rubber Pad Protects Desk】Wire organizer under desk built-in soft rubber pads on the clamp protect your desk from scratches, so you will not damage your furniture or office.
  • 【Sturdy and Beautiful】Cord management under desk is made of high-quality carbon steel and holds about 15 lbs. The wire basket has 2 holes on each side of the tray to enable your cables to pass freely. Cable baskets are suitable for desk thickness use from 0.4" to 2.4".
  • 【Space Saving & Keep Organized】Desk cable management tray holds all your power cords, outlet strips, USB hubs and computer transformers hidden from your feet, and the data cables will not enter the vacuum cleaner to keep your desk clean and tidy. Desk wire organizer is also suitable for use in the kitchen and outdoors.
  • 【Reduce Safety Risks】Cable tray under desk keeps all plugs away from your kids, no more worry about tripping. Using 2 holes wire tray saves extra space, helps you easily cabling and wire protection. The mesh design is not easy to accumulate dust, but avoids safety accidents caused by messy wires.

How to estimate a named reactor’s outage

For a specific unit, do not use the 75-day benchmark without checking the project configuration. The minimum information needed is:

  1. Confirm that the reactor is a pressurized-water reactor and identify the unit.
  2. Count the steam generators being replaced and note their size and arrangement.
  3. Find the planned refueling-outage start and target return dates.
  4. Determine how containment will be opened and how the heavy loads will be moved.
  5. List major concurrent maintenance, inspection and refueling work.
  6. Check for licensing reviews, inspection hold points and required startup tests.
  7. Compare the utility’s original plan with its latest forecast as work progresses.

If those details are unavailable, present 75–80 days as a broad benchmark and 60–120 days as a documented project range. Do not describe either figure as a guaranteed schedule for a current outage; current return-to-service dates require confirmation from the plant operator or regulator.

Does replacement guarantee years of continued operation?

No. Steam-generator replacement addresses the condition of those components, but it does not guarantee that the plant will operate for a particular number of years. The Nuclear Regulatory Commission reports that corrosion and cracking in older steam-generator tubing led to replacements at many facilities; the first U.S. replacement occurred in 1980.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

San Onofre replaced its steam generators in 2010 and 2011, then later shut permanently after additional tube-degradation problems. That history shows why a replacement project must be evaluated together with the new design, fabrication quality, operating controls and subsequent inspection results.

Bottom line for outage planning

For a pressurized-water reactor replacing steam generators during refueling, plan on approximately 75–80 days offline. A highly efficient project can finish in about two months, as Callaway did in 63 days 13 hours, while a larger or more complex outage can run to roughly three or four months, as the Catawba estimate and Watts Bar Unit 2 schedule illustrate. The decisive factors are the plant’s access and lifting configuration, the number of generators, concurrent work, weld and inspection results, and any licensing or emergent findings.