Sesterce has proposed an AI computing campus at the former Kaipola paper mill site in Jämsä, Finland, with planned investment of more than €10 billion. The proposed campus would start with a 200 MW first phase and could reach 600 MW in a second phase; neither capacity has been delivered, and the cited announcements do not establish that construction has begun.

What Sesterce is proposing

French AI infrastructure company Sesterce announced the project on October 8, 2026, and Jämsä City published a matching announcement that day. The site is the former Kaipola paper mill. Sesterce says it wants to reuse existing industrial infrastructure, including the power grid, water systems, buildings and logistics connections. Its CEO, Youssef El Manssouri, said the goal is to “preserve the area’s industrial identity” while making use of those assets. Sesterce’s announcement and the city’s announcement describe a proposal, not an operating campus.

The announced investment is more than €10 billion. Reuters rendered that as approximately $11.21 billion using the exchange rate in its October 8, 2026 report; the dollar amount is therefore a time-specific conversion, not a separate project budget. Reuters reported the announcement.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

How the planned capacity and schedule fit together

The 600 MW figure refers to the expected second phase, not the initial build or current capacity. Sesterce says work on a 200 MW first phase is planned to begin in 2026, with a second phase expected to raise the campus to 600 MW. It also describes a longer-term ambition to develop more than 1 GW of AI capacity in Finland across existing industrial sites and in line with market demand. These are company plans and ambitions; the announcements do not establish construction, commissioning or delivered capacity.

#1 Best Overall
Sale
HPE NVIDIA Tesla V100 32GB HBM2 PCIe 3.0 x16 Passive GPU Computational Accelerator for AI Machine Learning HPC Deep Learning 699-2G500-0216-400 (Renewed)
  • NVIDIA Volta GV100 Architecture — 4,608 CUDA Cores, 640 1st-Gen Tensor Cores delivering 14 TFLOPS FP32 and 112 TFLOPS deep learning performance for AI training, inference, HPC, and scientific computing workloads
  • 32GB HBM2 ECC Memory — 900 GB/s Bandwidth — High-bandwidth memory on a 4096-bit bus with ECC error correction provides the memory capacity and throughput required for the largest AI models, simulations, and datasets
  • PCIe 3.0 x16 Interface — 250W TDP — Standard PCIe Gen3 connectivity with passive cooling designed for enterprise rack server deployment in HPE ProLiant, Dell PowerEdge, and Supermicro platforms with adequate chassis airflow
  • NVLink — Scale to 96GB Unified Memory — Connect two V100 GPUs via NVLink at 300 GB/s bi-directional bandwidth to scale GPU memory from 32GB to 96GB for larger AI training and HPC workloads
  • Multi-Precision Computing — Supports FP64 (7 TFLOPS), FP32 (14 TFLOPS), FP16 (112 TFLOPS) and INT8 precision modes for flexible deployment across training, inference, and scientific simulation workloads
Stage Capacity or scale Status in the announcements
Jämsä first phase 200 MW Planned; work is intended to begin in 2026, according to Sesterce
Jämsä second phase 600 MW total campus capacity Expected future capacity, according to Sesterce
Longer-term Finland ambition More than 1 GW Company ambition across existing industrial sites, subject to market demand

Will the proposed campus go ahead?

The available announcements show a substantial proposal and a reported customer commitment, but do not establish that the project is fully financed, permitted or under construction. Sesterce says it has an anchor customer. Yle reported on October 9, 2026, that El Manssouri told the broadcaster an investment decision had been made and a contract signed with a future client, which he described as one of two leading AI laboratories. Yle said the client was not named; the project’s financial backers were also not public in the cited reporting. Yle’s report covers the customer statement.

The cited reporting does not establish permits, final financing details or the start of construction. Jämsä mayor Jori Reijula described the proposal as an interesting opportunity while stressing that it must move from plans to implementation and meet applicable requirements. The city says it will assess projects carefully as they advance. The practical signs of progress to watch are permitting and financing, a disclosed customer or backers, and construction and commissioning milestones—not the announced capacity alone.

Rank #2
GIGABYTE Radeon™ AI PRO R9700 AI TOP 32G Graphics Card, Turbo Fan Cooling System, 32GB GDDR6, GV-R9700AI TOP-32GD Video Card
  • Powered by Radeon AI PRO R9700 - Supercharge you workflow with the cutting-edge RDNA 4 Architecture and 2nd-gen AI Accelerators.
  • 32GB GDDR6 with 256-bit memory bus - Tackle larger, more complex projects without limits.
  • PCIe Gen 5 - Unlock lightning-fast data transfers with PCIe Gen 5 support.
  • GIGABYTE TURBO Fan Cooling System - Indented metal cover and blower fan increase airflow intake, while the vapor chamber, all copper heat sink, and metal frame offer efficient heat dissipation. Optimized airflow design allows for easy multi-GPU scalability.
  • Double Ball Bearing Fan - Delivers superior heat resistance and rotational efficiency for better performance and a longer lifespan compared to conventional sleeve fans.

What Sesterce says the project could mean locally

Sesterce projects approximately 2,000 construction jobs and around 300 positions once the campus is fully operational, and says it intends to use primarily Finnish contractors and subcontractors. These are estimates and intentions, not confirmed hiring or realized employment figures.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

The company also proposes a €10 million community fund upon commissioning, with Jämsä City and residents selecting projects. It says public-facing facilities such as restaurants and education or learning spaces could sit alongside the campus, while compute facilities would remain separate and secure. The announcement does not establish that these facilities or the fund have been delivered.

Rank #3
Nimo AI NAS, Agentic Computer Mini PC and AI Server, AMD Ryzen 7 PRO 8845HS(up to 5.1 GHZ, beat i5-1235u) up to 132TB ZFS Hybrid Storage, Dual 10GbE for 24hr AI Agent
  • [Local AI Inference & 70B Model Ready] Equipped with the AMD Ryzen 7 PRO 8845HS processor, NEXUS is engineered for heavy local AI workloads. With a full-size GPU bay, it runs 70B LLMs natively without an internet connection. Ideal for AI developers and tech enthusiasts who need private environment for coding and model testing.
  • [132TB Mass Storage with ZFS Integrity] Features a hybrid storage architecture (3×NVMe + 4×3.5" HDD) supporting up to 132TB. Utilizing the enterprise-grade ZFS file system and ECC memory, it prevents data corruption and bit rot—a must-have for professional photographers and video editors safeguarding 4K/8K RAW footage.
  • [OpenClaw-Driven Automation Workflow] The built-in OpenClaw execution layer allows complex automated tasks to be processed locally. Even when offline, your backup schedules and AI file organization continue seamlessly. Say goodbye to monthly cloud subscriptions and high latency.
  • [Dual 10GbE & USB4 Ultra-Connectivity] Experience server-class speeds with dual 10GbE ports and a 40Gbps USB4 interface. It enables multi-user real-time collaboration on large project files directly from the NAS, ensuring zero-lag editing for creative studios and production teams.
  • [Open-Source ZimaOS for Total Privacy] Running on the fully open-source ZimaOS, NEXUS ensures your data stays physically on-premise with no backdoors. It acts as a "Digital Fortress" for privacy-conscious families and small businesses who demand absolute data sovereignty.
Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.Support on Ko-Fi

Energy, cooling and water commitments

Sesterce says it will enable 1 MW of newly built renewable generation capacity in Finland for each 1 MW the campus consumes, within ten years of the campus becoming operational. The company describes its planning as based on “energy-efficient and flexible operations.” This is an announced commitment; the cited announcement does not document implementation or independent audit results.

For cooling, Sesterce says it plans a closed-loop liquid system supplemented by harvested rainwater and recycled water, with no drinking water used for cooling. These are proposed design and operating measures, not verified performance data. The cited sources do not provide measured energy or water-use statistics for the project.

Rank #4
ASRock Radeon AI PRO R9700 Creator 32GB Professional Graphics Card, 2920 MHz Boost Clock, GDDR6, AMD RDNA 4, AI-Accelerators, DisplayPort 2.1a, PCIe 5.0, Blower Cooler
  • Professional AI & Creator Workstation: AMD Radeon AI PRO R9700 GPU with 32GB GDDR6 is engineered for AI development, professional content creation, and compute-intensive workloads.
  • Massive 32GB Memory Capacity: 32GB of GDDR6 memory on a 256-bit bus provides ample bandwidth for large AI models, 8K video editing, and complex 3D rendering.
  • Advanced RDNA 4 with AI Accelerators: 64 Compute Units with 3rd Gen Ray Tracing and dedicated 2nd Gen AI Accelerators for groundbreaking AI performance and visual computing.
  • Professional Blower Cooling: Efficient single blower design exhausts heat directly out of the chassis, ideal for multi-GPU workstation and server configurations.
  • Enterprise-Grade Thermal Solution: Vapor chamber heatsink with industrial Honeywell PTM7950 thermal interface material ensures reliable cooling under sustained professional loads.

What to verify as the proposal develops

  • Whether the project obtains the required permits and reaches final financing.
  • Whether construction starts and when any capacity is commissioned, distinguishing the planned 200 MW first phase from the expected 600 MW total.
  • Whether Sesterce or the reported customer publicly identifies the anchor customer and financial backers.
  • Whether projected local jobs become actual construction and operational employment.
  • Whether the renewable-generation, cooling, water and community-fund commitments are implemented and independently documented.