AVAIO Digital’s Taurus data center campus in Brandon, Mississippi, had begun site work by September 10, 2025. The next announced targets are delivery milestones in 2027, but the available public updates do not confirm later construction progress or that the campus is operating.
What progress has been reported?
The project is AVAIO Digital Taurus, planned for East Metropolitan Center in Brandon, Rankin County. In an announcement dated September 10, 2025, AVAIO said site work had officially begun. The company named Yates Construction as general contractor and said the start followed an August 2025 Agreement for Electric Service with Entergy.
That September announcement is the latest dated physical-progress milestone in the sources reviewed. It establishes that site work had started by then; it does not establish how much work has since been completed. The developer’s project page also describes a groundbreaking update, but no later dated construction milestone or confirmation of operations is documented in the available sources.
Do these 3 things before closing this tab:
1Scan for outdated or missing drivers - takes under a minute2Repair Windows errors before they cause bigger problems3Fix the driver behind crashes, sound loss and screen glitchesWhat is the announced schedule?
The schedule has several distinct milestones, not one confirmed opening date. AVAIO said the campus was scheduled to be ready for occupancy in the first half of 2027. The Mississippi governor’s office likewise expected construction completion during the first half of 2027. Separately, the Edison Electric Institute’s large-customer project listing, accessed in 2026, lists 116 MW available in the first phase in 2027; the listing’s publication date was not established.
#1 Best Overall
- Save valuable floor space: 6U wall mount server cabinet Dimensions: 13.78" H x21.65" W x17.72" D.Maximum mounting depth is 14.2"
- Keep critical network equipment secure: glass door and side panels are lockable to prevent unauthorized access. Front door can be installed on either side of the front of the cabinet to satisfy your door swing orientation preference
- Easy equipment configuration: Fully adjustable mounting rails and numbered U positions, with square holes for easy equipment mounting with top and bottom punch-out panels for easy cable access
- Durability: Made of high quality cold rolled steel holds up to 110lb (50kg) (Easy Assembly Required)
- PCI & HIPPA and EIA/ECA-310-E compliant
First-phase power availability, construction completion, and readiness for occupancy are related but different milestones. These are published targets or forecasts, not confirmation that any has been achieved.
How large is the campus, and how much power is planned?
Published acreage figures differ by source: the City of Brandon’s August 22, 2025 announcement described a planned 175-acre campus, while AVAIO’s project page lists 329 acres. The reviewed sources do not explain the difference, so the figures should not be treated as interchangeable or reconciled by assumption.
Rank #2
- Save valuable floor space: 12U wall mount server cabinet Dimensions: 24.25" H x21.65" W x17.72" D. MAXIMUM MOUNTING DEPTH is 14.2".
- Keep critical network equipment secure: glass door and side panels are lockable to prevent unauthorized access; Front door can be installed on either side of the front of the cabinet to satisfy your door swing orientation preference
- Easy equipment configuration: Fully adjustable mounting rails and numbered U positions, with square holes for easy equipment mounting with top and bottom punchout panels for easy cable access
- Durability: Made of high quality cold rolled steel holds up to 110lb (50kg) (Easy Assembly Required)
- PCI & HIPPA and EIA/ECA-310-E compliant
AVAIO’s project page lists 1,036 MW of total baseload power: 536 MW of grid power and 500 MW of baseload power behind the meter. Those are developer-published project specifications. The city announcement separately said nearly 450 MW of capacity was expected online by 2027; it does not explain how that figure relates to EEI’s 116 MW first-phase listing. These numbers describe different published measures and should not be combined as if they were the same capacity milestone.
What do the $6 billion figure and job projections mean?
AVAIO and Mississippi and Brandon officials described the project as a $6 billion investment in 2025. This is an announced investment figure, not an audited accounting of money already spent. The governor’s office projected at least 60 direct high-tech jobs and hundreds of indirect jobs; those are expected outcomes, not current hiring totals.
Rank #3
- Sturdy:4u server rack is construct from cold rolled steel, with a weight capacity of 110lbs(50kg); Electrostatic powder coat prevents rust and corrosion,quality finish
- Direct use:Open and use, not having to assemble it.Network rack can be placed flat or mounted on the wall,also can be installed vertically under the table
- Design Features:maximum mounting depth of 14 in,cables can be fixed on the side panel;Open frame server rack achieves effortless inspection, replacement and assemble
- Installation:wall mount network rack is easy to install,with instructions or videos for reference;Equipped with multiple accessories, suitable for different needs
- Application:EIA/ECA-310-E Compliant;wall mounted 4u rack fits all 19" racks and cabinets to hold various IT, network, and AV equipment;wall mount rack available in 4U, 6U, and 8U to choose
The state approved the project for its Data Center Enterprises tax exemption and had previously provided assistance through the Site Development Grant Program. Rankin County and Brandon are also identified as assisting. The governor’s announcement does not quantify the full public cost or all incentive terms, and the available sources do not establish realized economic or community impacts.
Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.What remains unconfirmed?
- Construction progress after the September 10, 2025 site-work announcement.
- A confirmed completion, occupancy, or operating date.
- Current hiring or measured economic and community outcomes.
- An explanation for the difference between the 175-acre and 329-acre figures.
- The complete value and terms of public incentives or assistance.
The City of Brandon said it would share further project milestone and community-impact updates as available. Until a later dated update confirms them, the 2027 schedule and projected jobs remain plans rather than completed results.
Quick Recap