Public reporting supports a $30–33 billion estimate for construction across phases of the Abilene campus, but it does not verify the headline’s proposed $17 billion for chips, $3 billion for power, and $2.4 billion for construction. Those line items should be treated as an uncorroborated estimate, not a disclosed project budget. Scope matters: reports describe an eight-building flagship campus, a separate Microsoft expansion, and a later filing for one building, each with different cost and capacity boundaries.

Is the $30 billion figure supported?

Partly. On August 13, 2026, CNR Magazine reported a total construction cost of $30–33 billion across the Abilene campus’s construction phases. That is a campus-wide construction estimate as described in the report; it is not a verified itemized budget for building and equipping exactly 1 GW of capacity.

The available public figures use different definitions and project boundaries. A 2025 Texas Economic Development Council award submission said Project Radiance was expected to involve more than $47 billion in capital investment to develop eight buildings. That earlier capital-investment figure is not directly interchangeable with CNR’s later construction-cost estimate. Neither establishes the proposed chip, power, and construction allocations.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

What do the reported costs cover?

The $30–33 billion campus construction estimate

CNR’s August 2026 estimate concerns construction across campus phases. Its report identifies Crusoe as developer and DPR as general contractor for the then-current phase. The source does not provide a detailed accounting that confirms the headline’s separate equipment and power amounts.

#1 Best Overall
Tecmojo 12U Open Frame Network Rack for IT & AV Gear, AV Rack Floor Standing or Wall Mounted,with 2 PCS 1U Rack Shelves & Mounting Hardware,Network Rack for 19" Networking,Audio and Video Device
  • 【Powerful Load-bearing】12U Network Rack Open Frame is constructed from durable cold rolled steel; Rack shelf supports enhance stability, wall-mounted capacity of 130lbs, the ground-mounted up to 260lbs
  • 【Considerate Designs】Open-frame layout, including a top panel adding space, anti-slip shelf stops fixing devices and compatible racks for stack and expansion to meet requirements of home server rack
  • 【Complete Accessories】A 12U open frame server rack, two ventilated shelves, four shelf stops, four velcro straps and a set of equipment mounting screws
  • 【Versatile Application】Ideal for space-efficient multi-device setups in warehouses, retail, classrooms, offices and more; Excellent choices as AV Rack/IT Rack
  • 【Effortless Setup】 Network Rack includes hardware, a comprehensive manual, mounting hole drilling template and an online assembly video to simplify setup

The $6.3 billion Building 9 filing

A Texas Department of Licensing and Regulation filing, TABS2026008297, lists an estimated $6.3 billion cost for Abilene Building 9’s core and shell. The filing describes a 738,382-square-foot project, with a February 21, 2026 start date and an April 15, 2027 completion date. This is one building’s filing estimate—not the total cost of the flagship campus or the broader site.

The $3.5 billion economic-impact estimate

A February 2025 Perryman Group report estimated about $3.5 billion in gross product and 31,050 job-years from construction activity, including multiplier effects. These are modeled regional economic impacts, not the amount spent to construct the facility.

Rank #2
VEVOR 6U Wall Mount Network Server Cabinet, 14.8'' Deep, Server Rack Cabinet Enclosure, 200 lbs Max. Ground-Mounted Load Capacity, with Locking Glass Door Side Panels, for IT Equipment, A/V Devices
  • Space Saving: Maximum depth: 14.8". Use the wall mount network cabinet to maximize available space for retail locations, classrooms, back offices, network cabinets, and other locations where space is limited.
  • Fast Heat Dissipation: The server cabinet is designed with vents to optimize airflow and avoid critical IT equipment overheating. Heat sink holes in the top, bottom, and rear panels are more conducive to heat dissipation.
  • Sturdy Construction: Robust welded frame construction for durability and long service life. With 100 lbs wall-mounted load capacity and 200 lbs ground-mounted load capacity, you can place multiple devices in the server rack cabinet as needed.
  • High Security: The locked glass door ensures the security of data and equipment. Wall mount rack enclosure server cabinet is ideal for use in public places such as offices, effectively protecting the security of your devices.
  • Hassle-free Installation: Fully adjustable square-hole mounting rails of the wall mount server cabinet facilitate device installation. Wiring holes on the top, bottom, and rear panels provide you with easy cable routing.

What is included in the Abilene campus plan?

CNR described an eight-building, four-million-square-foot campus plan. Its account of the initial phase identified two operational buildings with approximately 200–300 MW of capacity, filled with NVIDIA GPUs. The campus uses high-density AI infrastructure and direct-to-chip liquid cooling, according to CNR.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

That description helps explain why a data-center project’s overall cost cannot be equated with its building shell alone: equipment and supporting infrastructure are substantial parts of an AI campus. But the reviewed public reporting does not establish the headline’s $17 billion chip allocation, $3 billion power allocation, or $2.4 billion construction allocation as actual project accounts.

Rank #3
VEVOR 12U Open Frame Server Rack, 23-40 in Adjustable Depth, Free Standing or Wall Mount Network Server Rack, 4 Post AV Rack with Casters, Holds All Your Networking IT Equipment AV Gear Router Modem
  • Adjustable Depth: 23-40'' adjustable depth is used for servers and network equipment, ensuring enough space for AV equipment, components, and cabling, while allowing you to access ports and equipment from multiple sides.
  • Strong Load Capacity: Ground-Mounted Load Capacity: 500 lbs, Wall-Mounted Load Capacity: 150 lbs. The av rack is made of carbon steel for better weldability performance and can help save space while meeting your need to place multiple devices.
  • User-friendly Design: Ergonomic design makes the open frame av rack easier to use. The additional top panel is able to place other items with more available space. Roller design moves anywhere and anytime, is convenient, and is more energy-saving.
  • Complete Accessories: We provide the accessories you need, including 2 x Pallets, 145 x M5*10 Cross Head Screws, 4 x Casters, 4 x M10*50 Expansion Screws,10 x M6*12 Cage Nuts, 1 x Grounding Wire, 1 x User Manual.
  • Wide Application: The server rack wall mount maximizes the use of available space, suitable for retail venues, classrooms, offices, and other places where space is limited.

Why the 1 GW label needs qualification

The sources describe a project that has changed in scope over time. CNR’s original flagship description covers an eight-building plan. In March 2026, the Associated Press reported on a neighboring Microsoft expansion that would bring the broader site to ten buildings and an expected 2.1 GW. The AP report also described a planned 900 MW on-site power plant for that expansion.

The expansion is not the same thing as the original flagship campus, and the combined-site capacity is not a basis for relabeling every reported cost as the price of exactly 1 GW. Capacity can refer to different boundaries or measures; the cited reports do not establish that the $30–33 billion construction estimate maps to precisely 1 GW.

Rank #4
AC Infinity CLOUDPLATE T2, Rack Mount Fan 1U, Top Exhaust Airflow
  • An intelligent fan system designed for cooling audio video, DJ, server, network, and IT equipment racks.
  • Protects rack-mount equipment from overheating, performance issues, and shortened lifespans.
  • Programmable thermostat controller with automated speed control, alarm warnings, and backup memory.
  • Premium anodized aluminum construction with CNC-machined detailing for a professional appearance.
  • Size: 1U Rack Space | Design: Top Exhaust | Airflow: 60 to 300 CFM | Noise: 12 to 38 dBA | Bearings: Dual Ball
Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.Support on Ko-Fi

How the campus is powered and cooled

Oracle’s Abilene project page says the campus connects directly to ERCOT and draws from the regional energy supply, including wind. Oracle says GE Vernova natural-gas turbines provide backup power. Separately, AP reported that the Microsoft expansion plan included a 900 MW on-site power plant and contrasted it with a 350 MW gas-fired plant attached to the OpenAI/Oracle project. AP said Oracle had described the latter as backup while the data centers primarily draw from the grid.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Oracle also describes its cooling system as a one-time-fill, closed-loop, non-evaporative system and estimates roughly 50,000 gallons per building annually for cooling maintenance. This is Oracle’s estimate, not an independently measured figure. CNR’s description of direct-to-chip liquid cooling identifies the technology approach, but does not independently verify Oracle’s water-use estimate.

How to read the figures without conflating them

Figure What it refers to Source and date
$30–33 billion Construction cost across campus phases as reported; not a verified 1 GW itemized budget CNR Magazine, August 13, 2026
$6.3 billion Estimated cost for Building 9 core and shell, 738,382 square feet Texas Department of Licensing and Regulation filing TABS2026008297; accessed 2026
More than $47 billion Expected capital investment to develop eight Project Radiance buildings, in an economic-development submission Texas Economic Development Council, 2025
About $3.5 billion gross product; 31,050 job-years Modeled construction-phase regional economic impacts, including multiplier effects; not construction spending The Perryman Group, February 21, 2025

These amounts should not be added together: they refer to different scopes, definitions, and purposes. In particular, the Building 9 filing is a single-building estimate, while the $30–33 billion figure is reported across campus phases; the more-than-$47-billion figure is capital investment stated in an earlier economic-development document.

What would verify the headline’s breakdown?

To treat the $17 billion, $3 billion, and $2.4 billion figures as project costs, readers would need a source that identifies who produced them, which project boundary and date they cover, and what each category includes. The available reporting provides no public accounting that confirms those line items. Until that accounting is available, the sound conclusion is narrower: a published report puts campus-phase construction at $30–33 billion, while the detailed breakdown and its relationship to 1 GW remain unverified.