EDF has received three replacement steam generators for the 900 MWe Unit 2 pressurized-water reactor at Cruas-Meysse in southeastern France. The verified 2026 account differs from the widely repeated description of four 474-ton units sailing around Spain and Portugal: EDF and Mitsubishi Heavy Industries document a Japan-to-Fos-sur-Mer shipment, a river-port transfer to Cruas and a final move on a special trailer. Installation is planned during Unit 2’s eight-month outage beginning in February 2027.
What arrived at Cruas-Meysse
EDF says the generators arrived by ship from Japan at Fos-sur-Mer, were transferred to the river port at Cruas and then hauled to the nuclear site. Mitsubishi Heavy Industries (MHI) manufactured them at its Kobe facility. French nuclear regulatory compliance was certified at the end of February 2026 before transport to France.
| Item | Verified detail |
|---|---|
| Number of generators | Three |
| Reactor destination | Unit 2, a 900 MWe pressurized-water reactor at Cruas-Meysse |
| Approximate size | 21 metres high and about 330 tonnes per generator |
| Heat-transfer tubing | About 4,500 TT690 nickel-chromium-iron tubes in each generator |
| Manufacturer | Mitsubishi Heavy Industries, Kobe, Japan |
| Storage plan | Preparation and storage in dedicated buildings until installation in the Unit 2 reactor building in 2027 |
These are bespoke primary-to-secondary heat exchangers, not ordinary boilers. Their dimensions and mass require a multimodal logistics plan and purpose-built handling equipment even though the reactor remains operating while the equipment is prepared.
The Tool Desk
Outbyte Driver Updater FREEFix the driver behind crashes, sound loss and screen glitchesFind Drivers →Outbyte PC Repair FREEClear out junk files and repair common Windows errorsFree Scan →How the generators were moved
Ship from Japan to Fos-sur-Mer
The first leg was an ocean shipment from Japan to Fos-sur-Mer, the major industrial port on France’s Mediterranean coast. EDF’s account identifies Fos-sur-Mer as the arrival port; it does not establish a voyage around Spain and Portugal.
#1 Best Overall
- Tailored for Multiple Spaces: 9kW steam generator fits 212-318 ft³ / 6-9 m³ steam showers, home saunas, and bathrooms. Compact size installs under vanities or in cabinets, ideal for tight spaces and custom setups
- Fast & Continuous Steam: Enjoy soothing steam in under 5 minutes and maintain consistent output from 10 minutes to 24 hours. Designed as a powerful steam shower generator, it auto-drains after use, offering a seamless home steam generator experience
- Smart Temp & Timer Control: Digital controller lets you set temperature (77-131°F / 25-55°C) and time (10-24h) with ease. Real-time indicators for heating, water shortage, and draining keep you in full control of your steam shower system
- Hassle-free Installation: Save time and cost with a full set of installation accessories and detailed step-by-step instructions. This steam generator is easy to set up in various residential or commercial condition
- Sturdy Build, Triple Protection: Constructed with a carbon steel exterior and SUS304 stainless steel inner tank, it corrosion-resistant and rust-proof. Triple security protections—overheat, dry-run, and overpressure, powerful and secure
River transfer to Cruas
From Fos-sur-Mer, the units were moved to the river port at Cruas. Using the river network avoids sending the full load through unsuitable stretches of public road and places the cargo close to the plant on the Rhône corridor.
Special trailer to the plant
The final leg used a specific heavy-haul trailer from the Cruas river port to the Cruas-Meysse site. Neither EDF’s 2026 notice nor MHI’s technical information verifies a 22-mile, three-day road crawl, a passage an inch from a roadside cross or any other precise roadside anecdote. Those details should not be treated as established facts for this delivery.
Rank #2
- PERFECT PERFORMANCE - Perfect steam experience is exactly what we had in mind with steam generators. Quickly produce a consistent flow of soft and smooth steam thanks to the cleverly designed dual tank technology ,while minimizing any distracting operational noises.
- INTELLIGENT CONTROLLER - Easily adjust temp and working time to your liking of 95 - 131℉and 30 mins-12 hours. Stainless Steel Tanks and Quality Components (Include Touch Screen Control, Aromatherapy Steam Head, and Cable) Ensure Enjoy Years of High Quality Steam in your bathroom and problem free operation.
- EASY TO INSTALL AND USE - Compact design permits installation in almost any small space near the shower, such as a vanity or closet.
- QUICK STEAMING AND WARMING UP - With auto drainage function, no need manual drainage, Quick steaming and warming up quickly, LED display segment heating, automatic segment heating, with automatic diagnostics and prompt information,More Intelligent and Lower energy consumption
- SAFE AND RELIABLE - Water shortage and overheat protection, with external light switch, automatic water inlet ,and automatic drainage. Quick Cleaning Port and Auto drain the water and limescale 15 minutes after each use Ensures Enjoy Fast and Clean Steam!
Why the generators can be stored before the reactor outage
EDF plans to prepare the equipment and keep it in dedicated buildings until the Unit 2 reactor building is ready for the replacement work. This separates transport and preparation from the radiological work inside the reactor building. The plant can therefore complete logistics, inspections and staging before the scheduled shutdown rather than tying the delivery timetable to the first day of the outage.
Outdated Drivers Are Slowing You Down
One free scan finds every outdated or missing driver and matches the right update for your exact hardware.Free scan · exact hardware matchPC Slower Than It Used to Be?
A free scan shows the junk files, broken settings and background clutter dragging Windows down - then fixes them in one click.Free scan · Windows 10 & 11Storage does not mean the generators are being installed immediately or that the reactor has already shut down. EDF’s schedule places installation in 2027, during the unit’s fourth ten-year inspection.
Rank #3
- WOOD BENDING STEAMER: The Earlex Steam Generator is the perfect tool to help you on your wood bending projects
- LONG RUN TIME: The 1.3 gallon tank will provide steam for up to 2 hours in enough volume for a small to medium size steam box. Plus, the exterior water level indicator will let you know when to refill
- PERFECT FOR ANY WORKSHOP: The small electric steamer uses a 1500 watt element to rapidly generate steam within your steam box. Its small footprint allows for convenient storage in any workshop
- SIMPLE INSTRUCTIONS: Includes instructions on how to build a steam box, and a steam box connector kit so you can be bending wood the same day
- BUILT-IN SAFETY FEATURES: The Steam Generator provides many safety features including a 12' cool to touch hose, thermal protection as well as an automatic suck back valve
What a nuclear steam generator does
In a pressurized-water reactor, the reactor core heats water in a sealed primary cooling system. That hot, pressurized water passes through thousands of tubes inside each steam generator. Heat crosses the tube walls into a separate secondary-water system, which boils into steam and drives the turbine-generator. The two water circuits remain physically separated.
MHI describes steam generators as among the most important components in a PWR because they provide the heat-transfer boundary between the reactor system and the turbine system. Tube material and integrity are therefore central to long-term plant reliability and safety.
Rank #4
- Built for steam box wood bending: The Touri steam generator creates a consistent steam source for steam boxes and wood-bending setups—ideal for chair parts, boat ribs, instrument sides, and workshop bending jigs
- 1.3-gallon capacity for longer sessions: The large tank provides ample steam output for up to 2 hours, helping reduce refill interruptions during multi-piece bending runs. Please add water promptly according to the external water level indicator
- Practical, portable workshop setup: Ideal for professional woodworkers, furniture factories, and craft studios. A 1500W heating element supports efficient steam production, so your steam box can reach and maintain optimal conditions for wood bending
- Built-in safety protections: Includes dry-run protection, auto shut-off, and a pressure relief valve for safe operation. Designed for wood steam boxes—do not connect to fully sealed containers. Please wear gloves and follow the manual during operation
- What’s in the box: Includes the steam generator unit, 12.3 ft hose, and brass connector. If you would like more information about the Touri steam generator, please reach out to us—we will assist you promptly
Why Cruas Unit 2 is shutting down in 2027
Fourth ten-year inspection
EDF says the outage is the fourth ten-year inspection for Unit 2 and is scheduled to begin in February 2027. The overall shutdown is planned to last eight months. Steam-generator replacement is expected to occupy about four months of that period.
Recommended Free Tools
Scale of the work
| Planning measure | EDF figure |
|---|---|
| Overall outage duration | Eight months |
| Steam-generator replacement phase | About four months |
| People involved in replacement | Nearly 400, working three shifts |
| Planned outage activities | 16,500 |
| Nuclear professionals on site | About 2,400 |
The inspection combines the generator replacement with the broader examinations, maintenance and modifications required during a periodic ten-year review. EDF frames the program as supporting operation beyond 40 years and moving the unit’s safety level closer to that of newer EPR designs.
What is and is not established about the headline claim
- Established: three generators, approximately 330 tonnes each, manufactured by MHI in Kobe; transport from Japan to Fos-sur-Mer, onward to the Cruas river port and then by special trailer; storage before 2027 installation.
- Not established in the official 2026 records: four generators weighing 474 tonnes each, a documented Spain-and-Portugal voyage, a 22-mile three-day road journey, the roadside-cross incident or exactly one year of storage.
The verified logistics are still a major engineering operation: each component is roughly 21 metres tall, contains thousands of heat-transfer tubes and must arrive in condition for a tightly scheduled reactor outage.
Quick Recap
Product prices and availability are accurate as of the date/time indicated and are subject to change. Any price and availability information displayed on Amazon at the time of purchase will apply.