ThisWay Global says it plans a phased, 73 MW research and AI compute center on 25 acres at Texas A&M-RELLIS in Bryan, Texas. The company says it closed a court-approved acquisition of the project assets on Sept. 30, 2026, and announced the plan on Oct. 8. The 73 MW figure is planned capacity—not confirmation that the site is built, connected to the grid, or operating.

What ThisWay Global has announced

The proposed Research and AI Compute Center (RACC) is intended to serve eligible research, public-sector, and industry users for research, advanced analytics, and other mission-critical AI and high-performance computing (HPC) workloads. Actual access would depend on contracting, procurement, security, and other requirements. ThisWay Global says it will use its Sovereign Blueprint framework and Amalgamy.ai software for governance and workload orchestration, but the final software deployment will depend on the operating model and customer needs. The company’s announcement does not establish a final operating configuration.

What the 73 MW figure does—and does not—mean

The company describes 73 MW as planned capacity for a phased project. It has not announced a committed power allocation, utility or interconnection approval, construction schedule, energization date, or start-of-operations date. Deployment phases remain dependent on engineering, approvals, utility arrangements, financing, procurement, and customer requirements. As a result, the announced figure should not be treated as the site’s current power use or as capacity already available to customers.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Cooling, water, and site design

ThisWay Global says the current design concept contemplates closed-loop, direct-to-chip liquid cooling. That is a preliminary design description, not a completed system or a quantified water-use estimate. The company has not published final engineering, a final cooling configuration, or the site’s water requirements; these remain subject to engineering and approvals. It also identifies noise, land use, and environmental requirements as planning matters. The announcement does not support a fixed water-footprint claim.

What the local tax agreement says

Brazos County’s record says the tax-abatement agreement for the RELLIS campus data and research center was originally approved on April 29, 2025, with RELLIS Campus Data and Research Center, LLC. County commissioners considered assigning it to ThisWay Global at their Aug. 18, 2026 meeting. The county notice reproduced in the Texas AI Docket gives a minimum estimated cost of approximately $700 million for improvements and tangible personal property.

KBTX reported that the county approved the transfer 4-0, with one commissioner absent, and that the Texas A&M University System Board of Regents and the City of Bryan had also approved transferring their agreements. KBTX described the county agreement as a 40-year structure: Brazos County receives 50% of taxable value for the first 10 years and 100% for the following 30. Those terms are attributed here to KBTX’s reporting; the agreement itself is not reproduced in the cited record.

How Texas’s data-center permitting context fits

On Sept. 21, 2026, the Texas Governor’s office announced that Gov. Greg Abbott had directed the Texas Commission on Environmental Quality (TCEQ) to halt data-center permits until the Electric Reliability Council of Texas (ERCOT) completes its audit. The release also discusses Public Utility Commission of Texas (PUCT) and ERCOT audits, water-use reporting, infrastructure-cost expectations, and setback requirements. The governor’s release provides statewide context, but the available project information does not establish how the directive applies to RACC or the status of any individual permit or approval.

Free tools Windows power users keep installed

One-click scans. No signup required.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.
Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.Support on Ko-Fi

What remains unknown about the Bryan project

  • Whether and when the project will receive a specific utility power commitment or interconnection approval.
  • Its construction milestones, energization date, and expected first operations.
  • The final cooling design and quantified water requirements.
  • Which project-specific permits are required, their status, and how the state directive affects them.
  • Which compute, cooling, construction, and connectivity vendors will be selected.

The project is therefore best understood as an announced development plan with a stated site, planned capacity, and preliminary cooling concept—not as an operating AI or HPC facility.