Moncalieri mayor Lorenzo Mauro has paused a proposed data-center campus at the former ILTE industrial site in the Vadò area because key questions about electricity supply, water use, cooling, discharges, land remediation, infrastructure and public benefits remain unanswered. The proposal is not an approved or operating data center: it is a negotiated executive-plan application still under municipal and technical review.

What happened to the Moncalieri data-center proposal?

The municipality’s transparency record shows that a negotiated executive-plan application was filed on 29 July 2026 for Via Fortunato Postiglione 14, the former ILTE site. Reporting identifies the applicant as the private company Moncalieri Logistics.

A services conference on 6 October examined the proposal and identified several unresolved technical and administrative issues. On 8 October, Mayor Lorenzo Mauro said the project was not acceptable at that stage because “there are too many things that still need to be assessed,” specifically including energy procurement and citizen involvement. On 13 October he repeated that “the project, as presented, is not acceptable” and called for a new discussion with the property owner.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Open reported that the latest conference findings had not yet been formally recorded when Mauro announced the pause. That means the pause is a political and administrative decision to require more work; it is not a final rejection or a construction approval.

#1 Best Overall
Tecmojo 6U Wall Mount Server Cabinet IT Network Rack Enclosure Lockable Door and Side Panels Black, Cooling Fan, Standard Glass Door, 450mm Depth, for 19” IT Equipment, A/V Devices
  • Save valuable floor space: 6U wall mount server cabinet Dimensions: 13.78" H x21.65" W x17.72" D.Maximum mounting depth is 14.2"
  • Keep critical network equipment secure: glass door and side panels are lockable to prevent unauthorized access. Front door can be installed on either side of the front of the cabinet to satisfy your door swing orientation preference
  • Easy equipment configuration: Fully adjustable mounting rails and numbered U positions, with square holes for easy equipment mounting with top and bottom punch-out panels for easy cable access
  • Durability: Made of high quality cold rolled steel holds up to 110lb (50kg) (Easy Assembly Required)
  • PCI & HIPPA and EIA/ECA-310-E compliant

What is proposed at the former ILTE site?

The submitted concept describes a large campus of four data-center buildings on approximately 270,000 square metres. Piemonte Regional Council documents and Rai TGR Piemonte reporting give the following figures:

Element Figure in the submitted concept Status
Data-center buildings Four Proposed, not finally approved
Site area About 270,000 sq m Approximate project description
Gross floor area 173,500 sq m Reported plan figure
Electrical capacity Up to 576 MW Maximum figure presented for the proposal, not an approved build-out
Planned employment 320 workers Stated target, not a guaranteed total
Land proposed for transfer to Moncalieri Almost 40,000 sq m Part of the negotiated offer
Works proposed by the property owner About €4.1 million Offer described during the planning process

The 576 MW capacity and four-building description describe the project as presented to the authorities. They should not be read as proof that all four buildings will be built, that the grid connection has been secured or that the campus will operate at that level.

Why did the mayor put the plan on hold?

Electricity supply has not been demonstrated

Mauro specifically listed electricity procurement as unresolved. The available record does not establish a binding grid-connection agreement, the source of the electricity, the delivery timetable or whether the local network can support the proposed maximum capacity. Those details are essential before a project of this scale can be assessed.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Water demand, cooling and discharges are unclear

The 6 October conference identified an unclear water requirement, an unspecified cooling system and incomplete information about how water or other discharges would be managed. No final water-consumption figure is established in the available reporting, so the proposal cannot be given a reliable annual water-use estimate.

Rank #2
AxcessAbles 12U Network Rack with Wheels - 500lb Capacity, 18" Depth | 19-Inch Open Frame AV Rack Case with 3” Caster Wheels | Screws, Spacer, Tool Included
  • Universal 19” Rack Mount Compatibility – Perfect for pro audio, video, IT, and network gear. Compatible with mixers, routers, patch panels, servers, power amps, and more.
  • Heavy-Duty Load Capacity – Built to support up to 550 lbs. Ideal for studio gear, DJ setups, server equipment, and AV components that demand serious stability.
  • Robust Steel Frame & Design – Made with 1.5mm thick steel and weighs 36 lbs for maximum durability, reduced vibration, and long-term reliability in any setting.
  • Mobile & Secure – Preinstalled with 3” industrial-grade caster wheels (lockable), making it easy to move and position your rack exactly where you need it.
  • All-In-One Setup Kit Included – Comes with 34 rack screws (5mm & 6mm), a 1U blank spacer, and an assembly tool—ready for fast installation out of the box.

The municipality also noted that an opinion from SMAT, the local water-service operator, was missing. Until the cooling technology, intake needs, treatment and discharge arrangements are documented and reviewed, the effect on water infrastructure remains undecided.

Remediation and public-green-space plans need more work

The area intended for public green space requires remediation. Authorities have not yet established the scope, schedule or responsibility for that work. Because the site is a former industrial area, remediation is a prerequisite for understanding what land can safely be reused and at what cost.

Hydraulic safety and impermeable surfaces remain open questions

The conference left unresolved issues involving hydraulic safety, the amount of impermeable surface and related urbanisation works. A campus with large buildings, roads and technical compounds can change drainage patterns; the municipal review therefore still has to determine whether the design meets local flood-risk and water-management requirements.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Municipal costs and the value of the public offer are unsettled

The property proposal included about €4.1 million in works and the transfer of nearly 40,000 square metres to the municipality. Municipal offices nevertheless raised concerns about the future maintenance burden of the transferred land and infrastructure. The offer is therefore not simply a headline benefit: Moncalieri must calculate long-term operating and maintenance costs before accepting it.

Rank #3
Sale
StarTech 22U 4-Post Server Cabinet, 33in/83cm Deep, 1764lb (RK2236BKF) | 19in enclosed enterprise steel rack, Adjustable depth 5.7in-33in, Lockable vented doors, Casters & feet
  • ADJUSTABLE DEPTH: 4- Post 22U 19" server rack enclosure with 4 vertical rails and adjustable mounting depth 5.7" to 33.0" (14,4cm to 83,8cm); IT rack is compatible with various servers / switches / data / video / AV and other IT networking equipment
  • EASY SHIPPING AND ASSEMBLY: Enclosed 22U data rack cabinet ships compact flat-packed to avoid damage and facilitate installation; Include wheels & levelling feet to offer more stability; Home server rack cabinet is only 46.6in (118,3cm) in height
  • DESIGN AND VENTILATION: Half height server rack cabinet has lockable and removable door and side panels with vented top allowing airflow; 4 Post 19" rack with 1764lb (800kg) weight capacity (stationary); Computer cabinet rack is EIA/ECA-310-E Compliant
  • HARDWARE INCLUDED: Rolling home network rack includes rack mounting and equipment mounting hardware, such as 20 M6 cage nuts / screws, PVC cup washers; Front/rear doors and side panels Keys, 2x allen keys; Rack assembly hardware; Casters and leveling feet
  • THE IT PRO'S CHOICE: Designed and built for IT Professionals, this 22U IT Server Cabinet is backed for life, including free lifetime 24/5 multi-lingual technical assistance

Noise, heat, generators and jobs need guarantees

Mauro also named noise, heat recovery, emergency generators and employment guarantees as issues still to be resolved. The record does not establish a final noise model, a binding heat-reuse scheme, generator operating conditions or a legally guaranteed number of jobs. The stated figure of 320 workers remains a plan target rather than an employment commitment.

How much power and water would it use?

The only published power figure is a maximum of 576 MW for the proposal as presented. That is a capacity figure, not a measured operating load or a confirmed utility contract. Actual demand would depend on the equipment installed, how many buildings are completed, utilisation and the final electrical design.

Authorities have not published a definitive water-demand number. Cooling technology and discharge management were among the items left unspecified, and the missing SMAT opinion prevents a final assessment of water-service impacts. Any more precise consumption claim would go beyond the documented evidence.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.
Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.Support on Ko-Fi

Who is behind the project?

Reporting identifies Moncalieri Logistics as the private company applying for the negotiated executive plan. The public record available for this decision does not establish a final investment amount, a binding financing structure, utility contracts or guaranteed employment terms. A figure of €5 billion appeared in an Open headline describing the wider “maxi-project,” but the cited material does not establish that amount as an approved or independently verified project cost.

Rank #4
NavePoint 12U Server Rack Enclosure with Glass Door, Cooling Fan, Locks, & Removable Side Panels - 12U Wall Mount Network Cabinet 19 Inch Rack 17.7" Deep (450mm)
  • DURABLE BUILD: Constructed from high-quality Cold Rolled Steel, the NavePoint Consumer Series 12U network cabinet boasts a sturdy, welded frame. Fitting EIA standard 19” networking equipment, this server cabinet confidently supports up to 110 lbs, providing a resilient base for your vital IT gear and equipment
  • CONVENIENT DESIGN: This 12U cabinet features a reinforced, heat-treated, tempered glass front door with a security lock. Perfect for applications requiring both security and accessibility, its compact design of 17.72"L x 21.65"W x 24.42"H offers a practical solution for space-constrained settings.
  • EASY & CUSTOMIZABLE EQUIPMENT SET UP - The 12U IT cabinet, with removable side panels and security locks, offers customization at its finest. Whether it's for an efficient device or cable management, this data cabinet ensures secure, adaptable configurations that suit your networking server requirements
  • ENHANCED VENTILATION & SECURITY - Built-in fans and flow-through ventilation work to prevent overheating, ensuring optimal operation of your equipment. The reinforced, lockable tempered glass front door not only boosts security but also facilitates easy monitoring of installed equipment.
  • SAFETY & COMPLIANCE - All NavePoint products are built to industry standards.

Will the data center be approved?

There is no approval decision to report. Mauro has committed the municipality to further discussion with the property owner, public involvement and additional technical review. The project could be revised, delayed or rejected; the current record does not support a prediction of the outcome.

Before a decisive municipal act, readers should expect the authorities to clarify:

  • the electricity source, grid connection and procurement terms;
  • cooling technology, water demand, treatment and discharge routes, including SMAT’s opinion;
  • remediation requirements and the conditions for creating public green space;
  • hydraulic-safety studies, impermeable-surface limits and urbanisation works;
  • noise, waste heat and emergency-generator impacts;
  • the value and maintenance obligations attached to land and infrastructure transfers; and
  • how the proposed employment figure would be guaranteed and monitored.

Why the dispute matters beyond Moncalieri

On 22 September 2026, the Piemonte Regional Council reported that the regional government was consulting stakeholders while preparing legislation to regulate digital infrastructure. Councillor Valentina Cera cited the Moncalieri proposal as an example of why municipalities need a clear, uniform and preventive framework.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

That regional work could affect how future data-center proposals address energy, water, land use, heat, emissions, resilience and community benefits before planning applications reach a final stage. For now, Moncalieri’s case illustrates the gap between announcing a large digital-infrastructure concept and proving that its utilities, environmental safeguards and public obligations are workable.