One free scan finds every outdated or missing driver and matches the right update for your exact hardware.Free scan · exact hardware matchiTechGuides is reader-supported. When you buy through links on our site, we may earn an affiliate commission. As an Amazon Associate I earn from qualifying purchases. Learn more
The safest way to cut data-center electricity is to measure facility power and IT power first, then remove avoidable computing load, correct airflow, tune cooling and electrical systems to actual demand, and verify reliability after every change. Keep designed fault tolerance intact: an efficiency improvement that removes required failover capacity is not a successful saving.
Start with a representative baseline, make reversible low-risk changes before capital projects, and judge results with workload, thermal, availability and recovery data—not PUE alone.
What to measure before changing anything
Collect electricity data for the whole facility and for the IT load over a period that represents normal operation. Include weekday and weekend behavior, peak and low demand, maintenance states, and typical weather where cooling is climate-sensitive. A short reading taken during an unusual workload can lead to the wrong investment.
Calculate PUE, but do not treat it as a complete efficiency score
Power usage effectiveness (PUE) is calculated as:
PUE = total facility energy ÷ energy delivered to IT equipment
#1 Best Overall
- Read Before You Buy — No Video Output: These adapters support charging and USB 2.0 data transfer, but cannot transmit video signals. Except for standard USB webcams (which use USB data only), they are not compatible with HDMI/DisplayPort cables, video-capable USB-C hubs, or docking stations with video output.
- Convert USB-A Ports to USB-C: Designed to connect USB-C earphones, cables, flash drives, card readers, and other USB-C accessories to standard USB-A ports. Plug-and-play with no drivers or software required.
- Aluminum Alloy Housing: Built with a sturdy aluminum alloy shell that aids in heat dissipation and protects against daily wear and scratches. Designed to maintain a stable and secure connection.
- Compact & Travel-Friendly: The ultra-compact design allows the adapter to stay plugged into your device without blocking adjacent ports or adding bulk, reducing wear and tear on your original USB ports.
- 12-Month Warranty: Backed by a 12-month manufacturer warranty for peace of mind. Designed to meet strict quality control standards for reliable everyday performance.
Total facility energy includes cooling, fans, pumps, lighting, power conversion and other infrastructure. IT energy is the electricity delivered to servers, storage and networking equipment. PUE is useful for seeing facility overhead, but it does not show how much useful computing the site delivers. A data center could improve PUE while doing less work, or have a stable PUE while serving more users with better IT efficiency.
Track IT energy and a useful-work measure alongside PUE. Depending on the facility, that may be virtual machines served, transactions completed, jobs processed, storage operations, or another agreed workload unit. Use the same definitions before and after a project.
Instrument at the rack and device level
Smart PDUs can provide rack-level or outlet-level readings, load trends, capacity information and abnormal-condition alerts. Combine those readings with UPS output, cooling-system meters, branch-circuit measurements and building-meter data. Record inlet temperature, humidity where relevant, airflow or differential pressure, fan and pump speeds, compressor state, UPS operating mode and available capacity.
Keep a change log. For each intervention, record the date, affected equipment, workload state, weather, alarms, maintenance activity and rollback procedure. Compare like operating conditions rather than comparing a cool low-load week with a hot peak-demand week.
Prioritize avoidable IT electricity
In a typical data center with highly efficient cooling, IT equipment can account for more than half of facility energy use, according to the U.S. Department of Energy’s Federal Energy Management Program and the National Renewable Energy Laboratory in 2024. Reducing IT load therefore lowers direct electricity use and can also reduce the heat that cooling systems must remove.
Inventory before decommissioning
Build an inventory that ties each server, storage system and network device to an owner, service, environment, utilization profile, power draw and recovery dependency. Look for equipment that is powered on but has no active owner, equipment retained after a migration, duplicate development systems, and capacity that is no longer required.
- Confirm that a device is not a standby node, monitoring appliance, backup target, licensing server or recovery dependency.
- Check recent CPU, memory, storage and network utilization rather than relying on a single snapshot.
- Verify maintenance contracts, software support and data-retention obligations before removal.
- Record asset identity and location so a mistaken shutdown can be reversed quickly.
Use a controlled shutdown or power-down test before physical removal when the service owner can validate behavior. Keep an approved rollback path until monitoring and business owners confirm that the service is unaffected.
Consolidate compatible workloads
Virtualization and workload consolidation can reduce the number of physical servers and the associated power and cooling demand. Consolidation is not automatically appropriate. Security boundaries, privacy rules, regulatory requirements, licensing, latency, hardware pass-through, service-level objectives and recovery architecture can require workloads to remain separate.
Rank #2
- 5-in-1 USB-C Hub: Experience comprehensive connectivity featuring a Power Delivery input, two USB-A 2.0 ports, a USB-A 3.0 port, and an HDMI port. (Note: The USB-C power delivery input port is only for connecting an external wall charger to power your laptop and cannot power peripheral devices.)
- 90W Pass-Through Charging: Achieve optimal charging with 90W pass-through power to your laptop, supported by a total input of 100W, with the hub reserving 10W for operational efficiency. (Note: Wall charger not included.)
- Quick Data Transfers: Accelerate your productivity with rapid data transfers using a high-speed 5Gbps USB 3.0 port and two 480Mbps USB 2.0 ports.
- 4K HDMI Display: Enhance your visual experience with a hub capable of delivering 4K resolution at 30Hz in both mirror and extend modes. Please note that this hub is compatible with MacBook (macOS 12 and newer), Windows 10 and 11, ChromeOS, and laptops equipped with DP Alt Mode and Power Delivery. Note: This device is not compatible with Linux.
- What You Get: Anker USB-C Hub (5-in-1, 4K HDMI), welcome guide, 18-month warranty, and our friendly customer service.
- Classify applications by performance, latency, data sensitivity, licensing and availability requirements.
- Measure actual resource use, including short peaks, batch windows and seasonal demand.
- Model the target host failure scenario, maintenance capacity and recovery time.
- Test the consolidated arrangement with production-like load and failure exercises.
- Move workloads in stages, observing host inlet temperatures, power draw, application latency and alarms.
- Retire surplus hardware only after capacity and recovery owners sign off.
Do not pack every workload onto the fewest possible hosts. A denser footprint can create rack hotspots, reduce maintenance headroom and increase the impact of a host failure. Preserve spare capacity required for failover and planned maintenance.
Choose efficient equipment at refresh time
When servers or network equipment are being replaced or added, evaluate efficient processors, fans, power supplies and network hardware. Efficient storage and power-supply consolidation can reduce both conversion losses and the number of active components. Replacing functioning equipment solely for an efficiency label may have a poor financial and environmental outcome if the embodied impact and disposal are significant; use measured power, expected service life and workload needs in the business case.
ENERGY STAR-certified servers and efficient power supplies are relevant options for new capacity. Certification does not make every model suitable for every workload, so compare performance at the required utilization and the equipment’s supported inlet-temperature range.
Free tools Windows power users keep installed
One-click scans. No signup required.
Correct airflow before making large temperature changes
Air-management work is often faster and less disruptive than replacing cooling equipment. The objective is to prevent supply air from bypassing IT intakes and to stop hot exhaust air from mixing with the air that servers must ingest.
Use a consistent aisle arrangement
Arrange racks so server intakes face a cold aisle and exhausts face a hot aisle, where the room and cooling design support that pattern. Seal openings that allow supply air to escape under floors or around cabinets. Rack blanking panels close unused rack spaces so exhaust air cannot recirculate through empty positions. Airflow grommets can limit leakage through cable openings when compatible with the raised-floor or overhead-air design.
Consider containment where mixing remains high
Hot-aisle or cold-aisle containment can isolate supply and return air. ENERGY STAR guidance describes potential containment energy-expense reductions of 5% to 10% in hot/cold-aisle data centers, but the result is site-specific and depends on existing airflow, controls, climate and load. The same guidance cites a DOE estimate that combining hot/cold-aisle arrangement with containment can reduce fan energy by 20% to 25%. Treat both figures as qualified estimates, not guaranteed savings.
Containment changes pressure and temperature relationships. Before installation, verify that cooling units, return paths, fire protection, access routes, cable work and emergency procedures remain compatible. After installation, inspect the densest racks first and trend inlet temperatures at the top, middle and bottom of cabinets.
What’s actually slowing this PC down?
Pick the symptom - the matching free tool is one click away.
Check for bypass and recirculation symptoms
- Large temperature differences between nearby rack inlets indicate uneven distribution.
- Hot spots that appear after consolidation may reflect insufficient local airflow rather than inadequate total chiller capacity.
- Fans running at high speed while some aisles remain cool can indicate bypass air or poor control-sensor placement.
- Blanking panels that are missing, damaged or incorrectly fitted can allow recirculation.
Use smoke visualization, airflow measurements or computational analysis where needed, but confirm findings with operating sensors. Do not block required equipment intakes or exhaust paths in pursuit of a tidy aisle.
Rank #3
- Sleek 7-in-1 USB-C Hub: Features an HDMI port, two USB-A 3.0 ports, and a USB-C data port, each providing 5Gbps transfer speeds. It also includes a USB-C PD input port for charging up to 100W and dual SD and TF card slots, all in a compact design.
- Flawless 4K@60Hz Video with HDMI: Delivers exceptional clarity and smoothness with its 4K@60Hz HDMI port, making it ideal for high-definition presentations and entertainment. (Note: Only the HDMI port supports video projection; the USB-C port is for data transfer only.)
- Double Up on Efficiency: The two USB-A 3.0 ports and a USB-C port support a fast 5Gbps data rate, significantly boosting your transfer speeds and improving productivity.
- Fast and Reliable 85W Charging: Offers high-capacity, speedy charging for laptops up to 85W, so you spend less time tethered to an outlet and more time being productive.
- What You Get: Anker USB-C Hub (7-in-1), welcome guide, 18-month warranty, and our friendly customer service.
Tune cooling to actual heat load
Cooling controls should respond to equipment inlet conditions and actual load rather than room averages or the maximum design load at all times. Review computer-room air-handler or air-handling-unit supply temperature, fan speed, chilled-water or refrigerant conditions, pump speed, economizer state and control dead bands.
Raise temperature only within equipment guidance
Higher server inlet temperatures can reduce compressor, fan and pump work, but the safe range is defined by the installed equipment and the applicable thermal guidance. The DOE/FEMP and NREL guide states: “Maximize compute entering temperature to maximize energy efficiency while ensuring information technology (IT) equipment thermal guidelines are met to avoid overheating or compromising reliability.”
Obtain the current manufacturer documentation for every relevant server, storage system and network platform. Use the most restrictive applicable limit when mixed equipment shares an intake environment. Configure high-temperature warnings below the shutdown or damage threshold, and define who responds to an alarm.
Quick wins for a faster PC:
Scan for outdated or missing drivers - takes under a minuteDriver Scan →Clear out junk files and repair common Windows errorsFree Scan →ENERGY STAR presents a general estimate that every 1°F increase can save 4% to 5% in energy costs. This is an undated checklist estimate, not a guarantee for every facility, and it should not be applied outside the installed equipment’s thermal envelope.
Use a controlled set-point procedure
- Confirm inlet sensors are calibrated and located where they represent the equipment, not just the room.
- Record baseline temperatures, humidity, cooling power, fan speeds and workload.
- Raise the set point in a small step during a stable operating window.
- Observe the highest rack-inlet temperatures, component alarms, fan behavior and application performance.
- Hold the change long enough to cover normal peaks and a representative weather condition.
- Roll back immediately if alarms, hotspots, throttling or service degradation appear.
Use economizers only when the site supports them
Air-side or water-side economizers can reduce compressor-based cooling when outdoor conditions are favorable. Suitability depends on local climate, humidity, air quality, filtration, water availability, system design and reliability requirements. Assess smoke, dust, corrosion, contamination control and seasonal transitions before enabling an economizer. A system that saves energy in mild weather but introduces unacceptable contamination or control instability is not an appropriate retrofit.
Review fans, pumps and cooling capacity
Fan and pump power can fall substantially when speed is reduced, but controls must still deliver the airflow and flow rate required at the most demanding zone. Verify variable-speed-drive operation, minimum-speed limits, filter pressure drop, coil condition and sensor placement. Correct clogged filters, failed actuators and leaking valves before changing design set points.
Match active cooling capacity to the heat load while retaining the redundancy required by the design. Staging one more cooling unit than necessary may provide resilience, whereas shutting down too many units can leave no margin for a failure or maintenance event. Document the minimum operating lineup for each failure mode.
The Tool Desk
Outbyte Driver Updater FREEScan for outdated or missing drivers - takes under a minuteDriver Scan →Outbyte PC Repair FREERepair Windows errors before they cause bigger problemsFix Now →Optimize UPS and power distribution without removing fault tolerance
Electrical losses occur in UPS systems, transformers, PDUs and cabling. Use trend data to identify lightly loaded equipment, phase imbalance, transformer losses and power conversion modes. Review UPS efficiency curves at the actual load rather than assuming the nameplate rating represents operating performance.
Rank #4
- Dual Converters, Infinite Potential:Includes 2× USB C male to USB A female adapters and 2× USB A male to USB C female adapters. Perfect for a wide range of uses—tablets with Bluetooth keyboards, expand USB ports on macbook, and more. Two different converters for all your daily needs
- Next-Level 10Gbps & 3A Charging: No more slow 480Mbps, this usb to usb c adapter has a transfer speed of up to 10Gbps, allowing you to do more transferring in less time. This usb adapter fits both USB A and USB C charger, supporting up to 3A fast charging
- Upgraded Exquisite Craftsmanship: With an aluminum alloy housing and metal connector, the usbc to usb adapter is extremely durable and sturdy. Rigorously tested to withstand more than 10,000 times of plugging and unplugging, ensuring long-lasting performance
- Broad Compatible: The usb c to usb adapter widely supports all USB C/ USB A devices like laptops, tablets, cellphones, car chargers, and phone chargers. Such as compatible with MacBook Pro/Air 2023/2022, Thunderbolt 4/3 Devices,Apple MagSafe Watch 9/8/7/SE/Ultra, iPad Pro 2022/2021, Samsung Galaxy S23/S20/S10, and iPhone 17/16/15 Pro. Plug and play
- Please Note: To reach 10Gbps speed, keep the cable under 3.3 ft. For USB A Male to USB C adapters, try flipping the USB C connector. USB C Male to USB A adapters support bidirectional 10Gbps transfer within 3.3 ft
Keep designed redundancy intact
Some UPS or PDU modules may be shut down when the required redundancy remains intact. ENERGY STAR specifically cautions that this decision depends on preserving the required fault tolerance. Before changing an operating lineup, engineering should verify:
- the intended N, N+1, 2N or other redundancy requirement;
- capacity after the largest single failure and during maintenance;
- selectivity, bypass paths and breaker coordination;
- generator, battery and transfer-switch behavior;
- thermal effects of concentrating load on remaining modules;
- alarm, monitoring and restoration procedures.
Never disable a module merely because its current load is low. A lightly loaded unit may be part of the failure capacity, maintenance strategy or distribution path.
Use outlet-level monitoring for capacity decisions
Outlet-level PDU measurements can reveal equipment drawing power without useful work, identify unexpected growth and improve rack-capacity planning. Monitoring itself does not reduce electricity use; it enables targeted actions. Set alerts for abnormal draw, circuit imbalance and unexpected changes, then route alerts to a team that can investigate them.
Recommended Free Tools
ENERGY STAR describes high-efficiency-transformer PDUs as 2% to 3% more efficient overall than generic lower-efficiency-transformer PDUs. Treat this as a product-category description rather than a promised saving for a particular installation. Compare measured loss, loading, bypass capability, maintenance requirements and compatibility with the existing distribution design.
Compare intervention options before approving a project
No single measure is universally best. DOE/FEMP notes that no design guide can offer “the most energy-efficient” data-center design for every scenario. Use a project scorecard that includes electricity, availability, thermal behavior, workload fit, cost, water, carbon, reversibility and detection speed.
| Measure | Electricity opportunity | Reliability and compatibility checks | Cost and implementation profile | Reversibility and detection |
|---|---|---|---|---|
| Remove genuinely unused equipment | Direct IT reduction plus less cooling load | Confirm ownership, dependencies, backup and recovery coverage | Usually low capital; requires inventory and change control | Highly reversible if shutdown is staged; service monitoring detects errors quickly |
| Virtualization or workload consolidation | Reduces host count when utilization and capacity allow | Check security, privacy, regulation, licensing, latency, failover and peak demand | Moderate engineering effort; may require migration and capacity work | Reversible by retaining source systems until validation; application and host metrics provide feedback |
| Blanking panels, grommets and aisle correction | Reduces bypass and recirculation; can lower fan and cooling work | Verify rack compatibility, pressure, cable paths and fire protection | Low to moderate capital; often quick to deploy | Easy to undo; inlet sensors and airflow checks reveal problems |
| Containment retrofit | Potentially significant cooling and fan reduction; ENERGY STAR cites 5%–10% energy-expense potential in some facilities | Check return paths, access, fire systems, pressure and dense-rack hotspots | Moderate capital and construction coordination | Partly reversible; temperature and pressure alarms should be reviewed continuously |
| Sensor-based cooling control | Reduces overcooling and fan or pump operation when controls respond to real load | Validate calibration, control limits, alarm ownership and fail-safe behavior | Moderate controls and instrumentation cost | Set-point changes are reversible; trend data exposes drift |
| Economizer operation | Can reduce compressor-based cooling in suitable conditions | Assess climate, humidity, contaminants, filtration, water and transition behavior | Low operating cost after installation; retrofit capital can be high | Control logic can be bypassed; weather and air-quality alarms are essential |
| UPS/PDU lineup or equipment change | May reduce conversion and transformer losses | Prove required redundancy, fault behavior, loading and maintenance capacity | Engineering-intensive; equipment replacement can be capital-heavy | Less reversible once hardware is removed; requires electrical testing and documented rollback |
Verify savings and reliability after each change
Use a before-and-after comparison with comparable workload and weather. Report total facility energy, IT energy, PUE, useful-work output, cooling energy, rack-inlet temperatures, alarms and availability. Explain any difference in operating conditions instead of attributing all movement to the project.
Run a post-change checklist
- Compare facility and IT electricity at the same measurement boundaries used for the baseline.
- Check workload throughput, utilization, latency and service-level results.
- Review inlet-temperature distributions, not only the average.
- Inspect hotspots after consolidation or containment changes.
- Review UPS, PDU, generator and cooling alarms, including nuisance alarms.
- Exercise failover and recovery paths affected by the change.
- Confirm that maintenance capacity and spare redundancy remain available.
- Keep the prior configuration and a time-bounded rollback plan until results are accepted.
Use a sustained observation period that includes normal peaks. A project is complete only when the measured reduction persists without unacceptable thermal, workload or availability effects.
Do these 3 things before closing this tab:
1Repair Windows errors before they cause bigger problems2Fix the driver behind crashes, sound loss and screen glitches3Clear out junk files and repair common Windows errorsCommon failure modes and corrective actions
PUE improves but electricity use does not
This can happen when IT load falls because less work is being delivered, or when facility boundaries change. Check IT energy and useful workload, then restore consistent measurement boundaries.
Best Value
- 5-in-1 Connectivity: Equipped with a 4K HDMI port, a 5 Gbps USB-C data port, two 5 Gbps USB-A ports, and a USB C 100W PD-IN port. Note: The USB C 100W PD-IN port supports only charging and does not support data transfer devices such as headphones or speakers.
- Powerful Pass-Through Charging: Supports up to 85W pass-through charging so you can power up your laptop while you use the hub. Note: Pass-through charging requires a charger (not included). Note: To achieve full power for iPad, we recommend using a 45W wall charger.
- Transfer Files in Seconds: Move files to and from your laptop at speeds of up to 5 Gbps via the USB-C and USB-A data ports. Note: The USB C 5Gbps Data port does not support video output.
- HD Display: Connect to the HDMI port to stream or mirror content to an external monitor in resolutions of up to 4K@30Hz. Note: The USB-C ports do not support video output.
- What You Get: Anker 332 USB-C Hub (5-in-1), welcome guide, our worry-free 18-month warranty, and friendly customer service.
Consolidation creates a hotspot
Redistribute workloads, verify rack airflow and add or correct blanking and containment measures. Do not solve a local airflow problem by lowering every room set point without investigating the distribution pattern.
Higher temperature causes throttling or alarms
Roll back the set point, confirm sensor accuracy and compare the affected equipment with its documented thermal limits. Mixed hardware may have different supported ranges.
UPS efficiency work reduces resilience
Restore the previous lineup and perform a formal redundancy and failure-mode review. A low-load module may have been required for N+1, maintenance or bypass operation.
Economizer operation is unstable or contaminated
Disable economizer operation while investigating humidity, air quality, filtration, damper control and changeover logic. Resume only after facilities and reliability owners approve corrected limits.
A practical order of operations
- Establish facility, IT, workload, thermal and power-system baselines.
- Remove or power down equipment proven to be unused, with rollback coverage.
- Consolidate compatible workloads while preserving capacity and recovery margins.
- Correct aisle arrangement, bypass airflow, blanking and cable openings.
- Tune fans, pumps and cooling controls to measured inlet conditions.
- Increase temperature only within the installed equipment’s documented guidance.
- Evaluate economizers, efficient PDUs and UPS changes with site-specific engineering.
- Verify electricity, workload, thermal behavior and failover results under comparable conditions.
This sequence favors measurable, reversible actions before changes that alter the power or cooling architecture. It also keeps reliability as a design constraint rather than a post-project check.
Frequently Asked Questions
Is PUE enough to prove a data center is energy efficient?
No. PUE measures facility overhead relative to IT energy. Pair it with IT electricity and a useful-work metric such as transactions, jobs or virtual machines served.
How much can raising the temperature save?
ENERGY STAR gives a general estimate of 4% to 5% in energy costs for each 1°F increase, but the figure is not a guarantee. Raise set points only within the actual equipment thermal guidance and with monitoring and rollback.
Can I shut down an underused UPS or PDU module?
Only after engineering verifies that the required redundancy, fault tolerance, maintenance capacity and bypass behavior remain intact. Low current draw alone is not sufficient evidence.
Should every server be virtualized?
No. Security, privacy, regulatory, licensing, latency, hardware and service-level requirements can make some workloads unsuitable. Validate capacity and recovery before retiring physical hosts.
What is the lowest-risk place to start?
Measure first, then investigate genuinely unused equipment and obvious bypass airflow. These actions are generally more reversible than changing electrical architecture or major cooling set points, but they still require ownership and dependency checks.