Data-center capacity is not a single megawatt, tonnage, or rack-count figure. Usable capacity is the amount of IT load that the utility connection, electrical distribution, cooling plant, rack and floor layout, environmental envelope, water and heat-rejection systems, resilience design, and delivery schedule can support at the same time. The limiting constraint sets the deployable capacity.

A repeatable plan therefore starts with power availability and schedule, describes the actual workload, models demand at rack and room level, translates that demand into heat and airflow requirements, selects a cooling topology that fits the site, checks physical and environmental constraints, and then validates the result through phased commissioning and monitoring. The method below is a planning framework, not a universal rack-density promise or a substitute for a stamped electrical, mechanical, structural, or code design.

What data-center capacity actually means

Different teams use the word capacity for different quantities. A utility planner may mean available megawatts at the point of interconnection. An electrical engineer may mean usable load after switchgear, transformers, distribution paths, and the selected redundancy arrangement. An operator may mean the IT load that can be installed without exceeding inlet-temperature, airflow, water, or maintenance limits. A leasing or deployment team may mean the number of racks that can be commissioned by a particular date.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Keep these quantities separate until the end of the planning process. Combining them too early hides the constraint that will stop a deployment.

#1 Best Overall
Sale
StarTech 8-Outlet 1U PDU, 120V/15A, Surge, 6ft Cord, TAA (RKPW081915)
  • POWER AND CHARGE: This rack mount power strip provides an additional 8 NEMA 5-15 outlets (120V/15A) and features a 6ft (1,8m) long cord so you can plug your devices in while leaving the rack mobile
  • 1U RACK DESIGN: Compatible with all 19" server racks 4 inches or deeper, this horizontal-mount power distribution unit fits many network racks and has an integrated power cord; ANSI/EIA RS-310-D standard
  • EASY INSTALLATION: This IT-grade rackmount PDU features a rugged steel chassis, LED indicators for ground and surge protection, and lets you control the power state with power and reset switches
  • PROTECTS YOUR EQUIPMENT: This rack mountable 8-outlet (120V) power strip features a built-in circuit breaker and reset switch, ensuring a dependable performance of your networking equipment
  • THE IT PRO'S CHOICE: Designed and built for IT Professionals, this rack PDU is backed for 2-Years, including free lifetime 24/5 multi-lingual technical assistance
Capacity layer Question it answers Planning output
Utility and site Can the grid and interconnection deliver the required power, and when? Available import capacity, expansion allowance, interconnection and permitting milestones
Facility electrical How much power can the distribution system deliver to IT while preserving the chosen resilience architecture? Usable electrical capacity by room, busway, panel, or branch path
IT load What equipment will actually be installed, in which phase, and with what replacement profile? Rack, row, room, and campus demand forecast
Thermal Can the cooling and airflow systems remove the projected equipment heat while keeping inlets within operating specifications? Cooling and airflow capacity by zone, including local hot-spot limits
Rack and floor Can racks, cabling, service clearances, and structural areas accommodate the equipment? Deployable rack positions and density limits by area
Resource and environmental Are water, heat rejection, climate, hazards, and operating conditions compatible with the design? Resource envelope and seasonal operating limits
Schedule and operations Can equipment, plant, commissioning, and future phases be delivered when the workload needs them? Phased capacity plan with dependencies and validation gates

A useful conceptual expression is usable IT capacity = the minimum of electrical, thermal, rack/space, resource, resilience, and schedule capacity. It is a way to reason about constraints, not a code calculation. The result changes when the workload, hardware, operating conditions, or expansion plan changes.

Start with site power and the delivery schedule

Power availability is often the earliest feasibility constraint. ASHRAE site-planning guidance recommends prioritizing power and utility infrastructure and coordinating with the utility early; interconnection work can take longer than building construction. A finished hall cannot be occupied if the substation, feeder, transformer, protection scheme, or utility approval is still pending.

Build a utility and schedule baseline

  1. Define the required service. Record the requested import capacity, voltage, service configuration, point of interconnection, and the phases in which load will appear. Keep the utility limit separate from the IT load target.
  2. Confirm what the utility can actually provide. Obtain written information on available capacity, substation constraints, studies, protection requirements, upgrade responsibilities, and expected interconnection dates. Treat an informal estimate as an assumption until the utility confirms it.
  3. Map expansion options. Identify whether additional feeders, transformers, switchgear lineups, or a new substation can be added without interrupting the first phase. Reserve physical space and routes for that work.
  4. Overlay permitting and procurement. Put utility studies, permits, long-lead transformers and switchgear, generator or energy-storage equipment where applicable, and commissioning activities on one schedule. The earliest missed dependency becomes the capacity date.
  5. Set decision gates. Do not release a major build phase on a nominal megawatt figure alone. Require confirmation of utility, equipment, site, and commissioning milestones for the phase.

Include the electrical distribution and redundancy architecture in this baseline. Two facilities with the same utility service can have different usable IT capacity because one reserves more equipment and path capacity for maintenance or failure conditions. Record which loads are supported by which distribution paths rather than counting nameplate capacity twice.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Describe the workload before assigning racks or square footage

Capacity planning starts with the equipment, not an average density assumption. Build a forecast of current configurations, planned deployments, workload mix, deployment phases, and equipment replacement cadence. Distinguish steady loads from bursty or accelerator-heavy loads, and identify where those loads will be placed.

Information to collect for each deployment wave

  • Equipment type and quantity, including servers, storage, networking, and specialized compute.
  • Manufacturer electrical requirements and the expected operating range, rather than a single generic rack value.
  • Expected quantity and location of racks or cabinets.
  • Deployment date, growth rate, and replacement or refresh date.
  • Power-distribution arrangement, including the intended feeds and rack-level distribution equipment.
  • Thermal operating limits, airflow direction, and any liquid-cooling connections.
  • Whether the load is a committed installation, a forecast, or an upper-bound scenario.

ASHRAE identifies both watts per area and kilowatts per rack or cabinet as common maximum-load measures. They answer different questions. Watts per square foot helps size rooms and compare broad layouts; rack or cabinet kilowatts exposes localized electrical and thermal peaks. A room that meets an average watts-per-area target can still have a row or cabinet that exceeds its power, airflow, structural, or service limits.

Use scenarios instead of one forecast

Create at least a committed case, a planned-growth case, and a high-load case that reflects plausible workload or hardware changes. Mark the assumptions that differ between them. The high-load case is not a promise that every rack will reach its maximum; it is a stress test for distribution, cooling, and expansion decisions. Refresh the scenarios when the equipment schedule or hardware generation changes.

Build rack-level and aggregate electrical views

Rack-level data is the bridge between a workload forecast and facility capacity. For each rack, calculate a configured demand from the equipment schedule, then aggregate it by row, room, and electrical distribution segment. Keep normal operating demand, expected peak demand, and any design maximum as separate fields so that a conservative boundary is not mistaken for a continuous load.

What’s actually slowing this PC down?

Pick the symptom - the matching free tool is one click away.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Recommended modeling sequence

  1. Inventory the equipment. List every planned device and its electrical requirement. Where the vendor gives a range, preserve the range and identify the value used for planning.
  2. Assign devices to physical racks. Include rack units, cable routes, service clearances, and the intended power feeds. Do not spread a high-density configuration across an average that no individual rack can achieve.
  3. Calculate rack demand. Sum the selected equipment values for each rack and document the operating condition represented by the sum. Keep a separate field for measured demand once the rack is commissioned.
  4. Aggregate by distribution boundary. Roll the rack schedule up to row, room, panel, busway, switchboard, and transformer levels. Check both total load and the most heavily loaded path.
  5. Apply the planned distribution and redundancy architecture. Identify which equipment is carried on each path and what capacity must remain available for maintenance, a failed component, or a future phase. The correct allowance is project-specific; do not insert a universal redundancy factor.
  6. Compare demand with available capacity. Evaluate the committed and scenario loads against the usable capacity of each electrical boundary, not merely the utility service rating.
  7. Version the model. Record assumptions, source documents, date, and responsible owner. Re-run it when equipment, workload, distribution, or phase dates change.

A rack-mount PDU can be part of the rack-level implementation, but selecting a physical PDU does not establish the facility’s safe loading limit. The branch circuit, protective device, distribution path, environmental conditions, and operating procedure remain part of the engineered design.

Interpret published rack-density observations correctly

The U.S. Department of Energy’s July 2024 design guide reports that high-performance racks were observed at about 60 kW in 2013 and have recently surpassed 125 kW. Those figures are historical and current observations cited by the guide, not a universal requirement, forecast, or design target. Use the equipment schedule and thermal design for the project rather than selecting a rack rating from a headline number.

Translate IT demand into heat and cooling requirements

Cooling capacity must match realistic projected equipment heat release and keep equipment within its specified operating envelope. A chiller or computer-room air-handler nameplate does not by itself prove that a rack can operate at its planned load. The thermal model has to connect equipment demand, airflow, inlet conditions, heat rejection, and seasonal operation.

Model the thermal boundary at the rack and room level

  • Use equipment-specific heat-release information tied to the same workload scenarios used for the electrical model.
  • Map supply-air paths, return-air paths, containment, and obstructions. Airflow separation can be as important as total cooling-plant capacity.
  • Check rack inlet conditions at the locations with the highest expected load. Room-average temperature can conceal a local hot spot.
  • Evaluate the operating envelope during normal operation, maintenance states, and credible equipment outages defined by the project resilience target.
  • Include the effect of deployment sequencing. A partially populated room may have different airflow patterns from the final state.

ASHRAE cautions that projected heat release can be assessed incorrectly and that a good facility cooling design matches capacity to actual heat load. Therefore, do not convert a facility-wide watts-per-square-foot assumption directly into a cooling promise without checking the rack distribution and local inlet conditions.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.
Rank #2
CyberPower CPS1215RM Basic PDU
  • 100-125V/15A Basic Power Distribution Unit (PDU) delivers AC power to data centers, network closets, and other electrically demanding applications
  • OUTPUT: 10 Rear NEMA 5-15R Outlets; INPUT: NEMA 5-15P straight plug with 15 ft power cord
  • VERSATILE RACKMOUNT OPTIONS: Allows for the PDU to be installed vertically or horizontally
  • ADDITIONAL FEATURES: Network-grade plugs and outlets, durable metal housing, and cord retention tray
  • 3-YEAR LIMITED WARRANTY (This unit does not provide surge suppression)

Separate cooling capacity from cooling availability

Cooling capacity is the heat-removal capability of the plant under specified conditions. Cooling availability also depends on pumps, fans, controls, distribution paths, water supply, heat-rejection equipment, maintenance states, climate, and the ability to deliver the required airflow or liquid flow to the rack. Document both. A plant may have enough nominal capacity while a blocked path, inadequate airflow, or a seasonal water limit prevents deployment in a particular zone.

Choose a cooling topology that fits density and site conditions

Cooling architecture should follow the workload and the site, not a predetermined density threshold. Air management and containment can improve the separation of supply and exhaust for many deployments. Higher-density configurations may require liquid cooling and facility-side equipment that a conventional air-cooled hall does not have.

Air management and containment

For air-cooled equipment, define supply and return paths, rack orientation, containment strategy, and control points. Verify that the design can maintain inlet conditions at the densest racks, not just at representative racks. Existing plant capacity, room geometry, climate, and the ability to route ducts or overhead services can determine whether an air solution remains practical.

Direct liquid cooling and heat exchangers

Where the equipment and workload require liquid cooling, include the complete facility-side chain: distribution piping, pumps, controls, heat exchangers, leak detection, maintenance isolation, and a heat-rejection path. The Uptime Institute identifies coolant distribution units as a cardinal design point for direct liquid cooling and also discusses rear-door heat exchangers. These components affect space, power, water, controls, commissioning, and operating procedures; they are not accessories that can be added after the room is full.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Compare topologies against site constraints

Planning question Air-focused design Liquid-capable design
What must be delivered to the rack? Separated supply and exhaust airflow with inlet conditions within equipment limits Liquid distribution, heat exchange, controls, and any required residual airflow
What site resources matter? Air-handler capacity, airflow paths, fan power, and heat rejection All air-system needs plus water or coolant management, CDUs or rear-door heat exchangers, and heat rejection
What changes during expansion? Containment, airflow balancing, and plant capacity must grow with rack demand Piping routes, CDU capacity, connection standards, leak controls, and plant capacity must be reserved
What determines suitability? Workload density, room geometry, climate, and existing plant Workload heat flux, equipment compatibility, facility-side infrastructure, water and climate constraints

No single topology is inherently best. Compare the whole system, including resource availability and the existing plant, rather than comparing only chiller or heat-exchanger ratings.

Check constraints beyond power and cooling

A rack that has electrical and thermal capacity can still be undeployable if it cannot be placed, serviced, supported, or connected. Review the following constraints before freezing the room plan.

  • Floor and rack footprint: reserve rack positions, aisle widths, service zones, staging areas, and routes for future plant and distribution equipment.
  • Structural loading: confirm that slabs, raised floors, equipment pads, and concentrated loads are suitable for the planned cabinets and mechanical or electrical equipment. The allowable value is project-specific and requires structural design.
  • Cable and service clearances: allow for power, network, piping, overhead or underfloor routes, bend radii, access doors, and maintenance removal paths.
  • Water and heat rejection: establish source, quality, treatment, discharge, seasonal availability, and the consequences of a restriction. Liquid cooling and some heat-rejection arrangements can change the water balance materially.
  • Climate and weather: assess ambient conditions, humidity, extreme temperatures, and weather events that affect free cooling, heat rejection, or equipment operation.
  • Hazards and site conditions: account for flood, fire, seismic, wind, contamination, and other hazards identified by the site and jurisdiction.
  • Expansion space: reserve room for future electrical and mechanical plant, not only empty rack positions. A full room can block the very infrastructure needed for the next phase.

Land, water, weather, hazards, and expansion are explicit site-planning concerns in ASHRAE guidance. The detailed floor-loading and clearance calculations belong in the project design package rather than in a generic capacity rule.

Set resilience and distribution assumptions explicitly

Capacity is meaningful only under a stated operating condition. Define which loads must remain online during maintenance, a component failure, or a planned transition, and identify the distribution paths that support them. Record the capacity reserved for those conditions instead of applying an unnamed percentage.

Free tools Windows power users keep installed

One-click scans. No signup required.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

At each electrical and cooling boundary, answer four questions:

  1. What is the normal operating load?
  2. Which components or paths are unavailable during maintenance?
  3. Which credible failure condition is included in the capacity calculation?
  4. How is the remaining capacity measured and restored after an event?

Use the same assumptions in the rack model, electrical single-line, mechanical sequence of operations, and commissioning scripts. If those documents use different definitions of available capacity, the apparent margin is not reliable.

Compare candidate capacity plans with a common scorecard

When choosing between a new hall, an expansion, and a retrofit, compare alternatives on the same axes. A plan with more theoretical megawatts may deliver less usable capacity if its interconnection arrives late, its cooling topology cannot support the workload, or it consumes the expansion space needed for later phases.

Rank #3
Sale
ElecVoztile 8 Outlet Rack Mount PDU Power Strip, 15A, 125V, 1875W
  • RACK MOUNTABLE: This 1U Rackmount PDU power strip fits 19" standard server racks and cabinets, featuring a 1U horizontal rack mount form factor that ensures compatibility with all 19" server racks.
  • 15A Overload Protection Switch: Provides overload protection by interrupting the circuit when the load exceeds the rated current.
  • HEAVY-DUTY: The power distribution unit features a heavy-duty construction, meticulously designed with robust components and housed in a durable aluminum alloy casing, ensuring a sturdy and long-lasting performance for reliable power management.
  • POWER CORD: The power distribution unit comes equipped with a 6-foot (1.8 meter) 14AWG power cord, providing flexible placement options and extended reach for versatile installation in various settings.
  • Commitment: ElecVoztile is dedicated to delivering superior products and outstanding customer service. Should you encounter any issues, please do not hesitate to reach out to us for immediate assistance.
Axis Evidence to compare Decision question
Utility and schedule Available utility MW, interconnection milestones, permitting, and equipment lead times Can the phase be energized when the workload requires it?
IT demand Rack-level, row-level, room-level, and campus IT kW for each workload scenario Does the plan support the actual equipment rather than an average?
Distribution and resilience Paths, reserved capacity, maintenance states, and failure assumptions What load remains supportable under the stated operating condition?
Thermal envelope Inlet conditions, airflow or liquid-flow capacity, hot spots, and seasonal limits Can the densest locations operate within specification?
Water and heat rejection Source, treatment, discharge, cooling topology, and climate dependence Are resource and environmental limits compatible with growth?
Footprint and expansion Rack positions, structural capacity, clearances, plant space, and routes Can future phases be built without removing the first phase?
Workload and refresh Deployment phases, expected growth, and equipment replacement cadence Will infrastructure outlive the assumptions used to size it?
Efficiency and operations PUE, water metrics where applicable, commissioning scope, and monitoring capability Can performance be measured and corrected after turnover?

This is a project comparison framework synthesized from the cited planning guidance, not a published universal scoring formula. Weight the axes according to the site’s schedule, reliability objective, resource limits, and workload.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Plan phases, commission the systems, and update the model

Design the first phase so that later capacity can be delivered without an unsafe improvisation. Show the future electrical rooms, cooling plant, piping, cable routes, structural zones, and control points on the expansion plan. Decide which items are installed initially, which are stubbed or reserved, and which require a new permit or utility study.

Use commissioning as a capacity test

  1. Verify installation. Check equipment ratings, protection settings, sensors, valves, controls, labeling, and physical clearances against the approved design.
  2. Test sequences. Exercise normal operation, maintenance states, transfers, alarms, and the resilience conditions defined in the project brief.
  3. Measure local conditions. Record rack or zone power, inlet temperatures, airflow or liquid-flow conditions, and plant response. Do not rely only on a building-level meter.
  4. Reconcile the model. Compare measured values with the rack schedule, thermal assumptions, and distribution limits. Correct the model before authorizing the next deployment wave.
  5. Operate with feedback. Monitor trends, investigate hot spots and unexpected load growth, and update assumptions when hardware or workload changes.

DOE defines power usage effectiveness as the ratio of total annual facility energy use to annual IT equipment energy use. PUE is useful for tracking facility-energy performance, but it does not state how much compute was delivered, whether a rack can accept another server, or whether the design meets a resilience objective. Use PUE alongside workload, thermal, availability, and water measures where applicable.

Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.Support on Ko-Fi

Common planning mistakes and how to correct them

Using one average density for every rack

Failure mode: A watts-per-square-foot target is multiplied by room area and treated as available rack capacity.

Correction: Build a rack schedule, identify the highest-load locations, and aggregate those loads through the actual distribution and cooling boundaries. Keep area density as a room-planning indicator, not a substitute for rack data.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Waiting for the utility decision

Failure mode: Building work begins on the assumption that an interconnection will arrive on the construction schedule.

Correction: Start utility studies, substation and feeder reviews, permitting, and lead-time checks at the beginning of site selection. Put written utility milestones on the integrated schedule.

Sizing cooling from a chiller nameplate

Failure mode: The plant rating is compared with a total IT figure while airflow paths, inlet temperatures, water, and seasonal heat rejection remain untested.

Correction: Model equipment heat release and local conditions, then verify the complete cooling path under normal, maintenance, and defined failure states.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Treating a dated density observation as a design target

Failure mode: The DOE observation of racks moving from roughly 60 kW in 2013 to more than 125 kW recently is used as a promise that every project should support 125 kW racks.

Correction: Treat the figures as context showing why localized planning matters. Use the project’s equipment schedule, thermal envelope, distribution, and expansion strategy to set rack limits.

Rank #4
Sale
BTU Power Strip Surge Protector Rack-Mount PDU, 8 Right Angle Outlets Wide-Spaced, Mountable Power Strip Heavy Duty for Server Racks, Commercial, 300J,ETL (Black 6FT)
  • 【Rack Mount Power Strip】: This PDU power strip surge protector equipped 8 wide space outlets (125V/15A), providing enough space between the sockets to large plugs. 8 in 1 power strip, features a 6 ft long cord so you can plug your devices in while leaving the rack mobile
  • 【1U Rack Mount Design】: 19 inch power strip compatible with all 19” server racks. The power distribution unit is designed for rack enclosure, garage, workshop, office, cabinet, work bench, wall mount, under counter and other mount installation applications, provides a neat look to your work station
  • 【Metal Wall Mount Power Strip】: The 1U PDU can be mounted horizontally or Vertically in any server rack 19" in depth, and features a rugged steel casing to ensure maximum durability;Equipped 4 screws to help mount and provided several mount way, you can release the screws on both sides and rotate the mounting bracket to the right angle for installation
  • 【Protects Your Equiement】: Our rackmount Power Strip features a built-in circuit breaker,and covered ON/OFF switch,300 Joules surge protector designed, it will automatically cut power to protect connected devices when voltage surge is overwhelming,ensuring dependable performance of vital data center equipment,Rackmount Surge Protector provides critical power protection for data centers and network closets
  • 【Warranty and Customized products】: 12-month warranty. Our factory specializes in power strips socket production, we provide product customization services for various outlets and extension cord,If you have any problem, please contact us without hesitate, we are always for you

Ignoring refresh cycles

Failure mode: Infrastructure is sized for today’s equipment while the facility is expected to operate through several hardware generations.

Correction: Model replacement cadence and plausible future configurations. Reserve electrical, thermal, structural, and routing capacity where later equipment could change the load profile.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Counting resilience capacity twice

Failure mode: The same megawatt or cooling module is counted as available on multiple paths, even though it is reserved for maintenance or a failure condition.

Correction: Trace each load to its distribution path and state exactly which components are available in each operating condition. Use the residual capacity, not the sum of nameplates.

Leaving expansion until the room is full

Failure mode: Rack positions are reserved, but there is no space or route for additional switchgear, pumps, piping, heat rejection, or controls.

Correction: Draw future plant and distribution on the initial plan and protect its structural, service, and access requirements.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Stopping at design completion

Failure mode: The model is never reconciled with commissioned measurements, so unrecognized hot spots or load growth accumulate.

Correction: Make commissioning, local measurement, trend review, and model updates release conditions for each deployment phase.

A repeatable capacity-planning worksheet

Use the following sequence for a new hall, expansion, or retrofit. Keep the outputs in a controlled document with an owner and revision date.

  1. Define the capacity boundary: site, building, room, row, or rack.
  2. Record utility availability, interconnection status, expansion options, permitting, and critical-equipment lead times.
  3. Document the workload, equipment schedule, phases, growth assumptions, and refresh cadence.
  4. Assign equipment to racks and calculate configured demand for each scenario.
  5. Aggregate rack demand through rows, rooms, panels, busways, switchboards, transformers, and utility service.
  6. State the distribution and resilience assumptions for normal, maintenance, and defined failure conditions.
  7. Model equipment heat release, airflow or liquid flow, inlet conditions, hot spots, and seasonal operation.
  8. Select and compare cooling topologies, including facility-side liquid-cooling equipment where required.
  9. Check footprint, structure, clearances, cable and service routes, water, heat rejection, climate, hazards, and future plant space.
  10. Build an integrated delivery schedule and identify the earliest dependency that can delay usable capacity.
  11. Commission the installed systems, measure local electrical and thermal conditions, and reconcile the model.
  12. Release later phases only after measured conditions and updated assumptions remain within the approved envelope.

The outcome is a documented, revisable capacity envelope tied to a real workload and site. It is more useful than a single rack-density claim because it shows which constraint controls today, which one may control the next phase, and what evidence is required before adding load.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Quick Recap

Bestseller No. 2
CyberPower CPS1215RM Basic PDU
CyberPower CPS1215RM Basic PDU
OUTPUT: 10 Rear NEMA 5-15R Outlets; INPUT: NEMA 5-15P straight plug with 15 ft power cord; VERSATILE RACKMOUNT OPTIONS: Allows for the PDU to be installed vertically or horizontally
$63.95

Product prices and availability are accurate as of the date/time indicated and are subject to change. Any price and availability information displayed on Amazon at the time of purchase will apply.