CtrlS has signed a non-binding Letter of Intent (LoI) with the Bihar government for a proposed 150 MW hyperscale AI data center at Bodh Gaya. The announced investment is ₹10,000 crore, approximately US$1 billion. Separately, the company has inaugurated a ₹400-crore facility in Patna’s Patliputra Industrial Area, giving Bihar additional data-center capacity that can serve customers sooner.
What CtrlS has announced
The Bodh Gaya project is planned as a 150 MW hyperscale facility focused on artificial-intelligence workloads. Data Center Dynamics reported the LoI and investment announcement on October 15, 2026. The agreement is with the Bihar government and is non-binding, so it records an intention to pursue the project rather than confirming that construction or financing is complete.
Contemporaneous reporting put the planned investment at ₹10,000 crore, or about US$1 billion. No public source identified a final building design, hardware platform, anchor customer, power mix or detailed construction phases.
Where the projects are located
Bodh Gaya: proposed AI campus
The proposed 150 MW site is in Bodh Gaya, a major destination in Bihar. Its announced role is to provide hyperscale AI infrastructure, potentially supporting high-density computing and cloud services for eastern India. The location and capacity have been announced, but a commissioning date and operational address within Bodh Gaya have not been supplied.
#1 Best Overall
Patna: inaugurated Patliputra Industrial Area campus
The nearer-term project is in Patna’s Patliputra Industrial Area. Bihar Chief Minister Samrat Choudhary inaugurated the facility, which was reported to have an initial IT load of 12 MW. CtrlS describes the campus as serving enterprises, government institutions, hyperscalers and technology companies in Bihar and the wider eastern-India market.
Patna capacity and what is operating
CtrlS’s Patna facility information lists two sites:
| Site | Listed IT load | Reported status or role |
|---|---|---|
| Patna Edge DC 1 | 0.50 MW | Part of the Patna edge-data-center footprint |
| Patna Edge DC 2 | 11.6 MW | Part of the Patna edge-data-center footprint |
The two listed loads total 12.1 MW, which is broadly consistent with the 12 MW initial IT load cited in inauguration coverage; the figures come from different descriptions and should not be treated as a revised engineering specification. CtrlS’s December 2025 company blog had described the expansion as a ₹400-crore, 10 MW edge data center. That earlier figure was a company description, while the later inauguration report gives the currently reported initial load as 12 MW.
The Tool Desk
Outbyte Driver Updater FREEFix the driver behind crashes, sound loss and screen glitchesFind Drivers →Outbyte PC Repair FREERepair Windows errors before they cause bigger problemsFix Now →The Patna site is described as carrier-neutral, with multi-zone security and connectivity intended to support regional digital transformation. In practical terms, customers can use it for colocation, connectivity and related infrastructure without waiting for the proposed Bodh Gaya campus.
How the Patna and Bodh Gaya projects differ
| Comparison point | Patna facility | Bodh Gaya facility |
|---|---|---|
| Status | Inaugurated facility | Proposed under a non-binding LoI |
| Location | Patliputra Industrial Area, Patna | Bodh Gaya, Bihar |
| Announced IT capacity | 12 MW initial load in inauguration reporting; CtrlS lists 0.50 MW and 11.6 MW sites | 150 MW planned hyperscale capacity |
| Announced investment | ₹400 crore | ₹10,000 crore, approximately US$1 billion |
| Intended users | Enterprises, government institutions, hyperscalers and technology businesses | Hyperscale AI workloads; specific customers not named |
| Schedule evidence | Inaugurated and presented as available capacity | No construction timetable or commissioning date stated |
Is the Bodh Gaya AI data center already operating?
No. The available announcement establishes a proposed project under an LoI, not an operating data center. An LoI does not by itself demonstrate that financing has closed, land and utility agreements are final, grid capacity has been secured, equipment has been ordered, construction has started or customers have signed contracts.
Until CtrlS or the Bihar government publishes evidence of those milestones, the 150 MW figure should be read as planned capacity. It is not current live capacity in Bihar and should not be added to the operating Patna load.
Rank #4
What the announcement could mean for eastern India
More regional capacity
The Patna campus can provide a local colocation and connectivity option for organizations that previously had to place workloads in other Indian data-center markets. Local infrastructure can reduce network distance for Bihar-based applications and give public institutions and businesses a regional site for hosting and disaster-recovery planning.
Potential AI-scale compute
If the Bodh Gaya project is executed at its announced scale, 150 MW would be substantially larger than the Patna facility and could expand eastern India’s access to AI-oriented compute and cloud infrastructure. The real effect will depend on the final design, power availability, network routes, customer demand and the amount of capacity delivered in each phase.
Best Value
- Family farms not data design for people against AI server farms, data center expansion, rural land buyouts, corporate agriculture, and industrial tech development replacing farmland and open space. Rural conservation and anti data center message.
- AI protest design for farmers, land conservation supporters, anti AI activists, sustainability groups, environmental advocates, rural communities, and people opposing server farm construction, power grid strain, and farmland destruction.
- Lightweight, Classic fit, Double-needle sleeve and bottom hem
Industrial and technology development
Chief Minister Samrat Choudhary said the project and Patna inauguration would establish a new foundation for technological development and industrial transformation in Bihar. CtrlS founder and CEO Sridhar Pinnapureddy said the company intends to strengthen Bihar’s digital infrastructure and build an IT ecosystem for hyperscalers, enterprises and startups. Those statements describe the intended economic direction; they do not guarantee jobs, customer numbers or a completed Bodh Gaya campus.
Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.What to watch next
- A binding development agreement, land allocation or environmental and construction approvals for Bodh Gaya.
- Financing closure and a published construction or phased-delivery schedule.
- Utility announcements covering grid connection, redundancy and the source of power.
- Confirmed equipment plans, including whether the facility will be optimized for GPU-intensive AI workloads.
- Named anchor tenants or signed capacity commitments.
- Commissioning evidence showing how much of the 150 MW plan has actually entered service.
For customers evaluating infrastructure now, the inaugurated Patna campus is the concrete opportunity. Bodh Gaya is a potentially transformative addition, but its commercial and regional impact cannot be measured until execution milestones move beyond the LoI.