Brightray Science Inc. is pursuing a planned 10MW AI data center in Indiana under a non-binding letter of intent (LOI) with an unnamed U.S. mission-critical infrastructure partner. The announcement makes this Brightray’s first U.S. project opportunity, but it is not confirmation that the facility will be built or become operational.
Brightray announced the LOI on October 14, 2026, after its wholly owned subsidiary, Brightray Veridian Pte. Ltd., signed it on October 6. The partner intends to issue a purchase order by November 15, 2026, while the LOI remains subject to technical, commercial, approval and contracting decisions.
What Brightray announced
The proposed Indiana facility would be a single-storey, prefabricated data center designed for high-density AI equipment. Brightray says its subsidiary signed the LOI with a U.S.-based mission-critical infrastructure partner, but neither the partner’s name nor the Indiana city or prospective tenant has been disclosed.
| Item | Details |
|---|---|
| Project capacity | Planned 10MW AI data center |
| Location | Indiana, with the city not disclosed |
| Commercial status | Non-binding LOI signed October 6, 2026 |
| Announcement date | October 14, 2026 |
| U.S. partner | Unnamed U.S. mission-critical infrastructure company |
| Prospective purchase order | The partner intends to issue one by November 15, 2026 |
| LOI term | Expires 12 months after signing unless replaced earlier by a definitive agreement |
Is the 10MW Indiana data center confirmed?
No. The LOI records an intended cooperation framework, not a binding construction award. Implementation depends on agreement over technical specifications, commercial terms, schedule, regulatory and other approvals, and definitive contract documents. Brightray explicitly says there is no assurance that a definitive contract will be signed, that a purchase order will be issued, or that the project will be completed as planned.
#1 Best Overall
The November 15 purchase-order date is therefore a target expressed by the prospective partner, not evidence that procurement has been completed. The project’s final scope, contract value, exact site and construction start are also undisclosed.
How the prefabricated data-center approach would work
Brightray’s proposed delivery model moves a substantial portion of the work into a factory before modules reach Indiana.
Factory work
The intended factory scope includes pre-installation and integration of data-hall modules and related functional systems. This approach is meant to standardize assembly and allow equipment integration to proceed under controlled conditions.
The Tool Desk
Outbyte Driver Updater FREEFix the driver behind crashes, sound loss and screen glitchesFind Drivers →Outbyte PC Repair FREERepair Windows errors before they cause bigger problemsFix Now →Rank #2
Site work
On site, crews would place the modules, make interface connections and complete integrated commissioning. The site program would still include foundation and ancillary works, permitting, shipping and the physical installation needed to connect the prefabricated systems.
Parallel schedule
Brightray is targeting delivery within one year, with factory prefabrication running in parallel with site work. The company says that target covers design finalization, permitting, international shipping, site foundation and ancillary works, installation and commissioning. The announcement does not define the schedule’s starting date; that starting point and the final conditions are to be established in a definitive contract.
What the proposed technical targets mean
NVIDIA GB300 compatibility
The intended design is described as compatible with NVIDIA’s GB300 platform. “Compatible” is a design target at this stage, not confirmation that GB300 systems have been installed, tested or accepted at the Indiana site. The release does not identify the final server configuration, rack density, liquid-cooling arrangement or power-delivery architecture.
Rank #3
Tier III design basis
Brightray says the facility is planned around a Tier III design basis. In practical terms, a Tier III data-center design is generally intended to allow planned maintenance on capacity and distribution components without shutting down the IT load. The announcement does not say that the proposed facility has been certified, and a design basis is not the same as an operating certification or demonstrated availability result.
Quick wins for a faster PC:
Fix the driver behind crashes, sound loss and screen glitchesFind Drivers →Clear out junk files and repair common Windows errorsFree Scan →Scan for outdated or missing drivers - takes under a minuteDriver Scan →Annual PUE below 1.2
The project’s target annual power usage effectiveness (PUE) is below 1.2. PUE compares total facility energy with the energy used by IT equipment, so a lower value indicates that less overhead power is planned for cooling, power conversion and other infrastructure. This is a planned efficiency target; no independently measured operating PUE has been reported.
Why Brightray is targeting the U.S. and Indiana
Brightray describes the United States as the world’s largest data-center market and says AI infrastructure customers are under pressure to convert investment into usable computing capacity quickly. Its release cites JLL’s 2026 Global Data Center Outlook as estimating that approximately 50% of global data-center capacity is in the Americas and approximately 90% of Americas capacity is in the United States. Those figures are reported by Brightray’s announcement rather than independently verified here.
The same release cites CBRE’s 2026 U.S. Real Estate Market Outlook for continuing power and infrastructure constraints that can affect data-center schedules. For this project, those constraints could influence site selection, utility interconnection, permitting and the timing of foundation and electrical work. No Indiana utility, parcel, power-availability date or grid-interconnection agreement has been disclosed.
Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.What could determine whether the project proceeds
- Definitive commercial agreement: The parties must replace the LOI with binding contract documents and settle pricing, responsibilities and payment terms.
- Technical freeze: Final decisions are needed on the AI equipment, power distribution, cooling, module interfaces and commissioning requirements.
- Permits and approvals: The one-year target includes permitting, but no permit status has been announced.
- Logistics: International shipping, site access and module placement must align with foundation completion and local works.
- Power and site readiness: High-density AI equipment requires sufficient electrical capacity and cooling infrastructure; the release provides no confirmed interconnection or utility schedule.
- Execution evidence: A purchase order, named site, construction start and completed commissioning would each represent a later level of commitment than the current LOI.
What to watch next
- Whether the prospective partner issues the intended purchase order by November 15, 2026.
- Whether Brightray and the partner sign a definitive agreement before the LOI expires on October 6, 2027.
- Disclosure of the Indiana city, site, tenant or utility arrangements.
- Publication of final technical specifications, permits and a contractually defined delivery schedule.
- Evidence that modules have been manufactured, installed and commissioned, rather than only planned.
Brightray’s stated rationale
“Entering the U.S. market is an important step in Brightray’s international development. The U.S. has enormous data center demand, and customers face real pressure to turn their AI investments into usable computing power as quickly as possible. Our entry point is delivery: with Brightray prefabricated data center solution, we move more of the work into the factory and run manufacturing in parallel with on-site works, with the aim of shortening the delivery period for this project to within one year.”
Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.Bin Wang, Brightray founder
The practical significance of the announcement is therefore its proposed delivery model and U.S. market entry, not a completed facility. Until binding contracts, approvals and construction evidence emerge, the Indiana data center should be described as a planned 10MW project under an LOI.